Air Motor Duty Selection Worksheet

5 min read9 sections

Interactive resource

Use the working tool for this page

This page has a matching worksheet, calculator or comparison resource. It runs in your browser: enter your own measured values and keep the evidence behind every result.

Open resource

Route: /engineering-tools/air-motor-duty-selection-worksheet/ (proposed until route reconciliation). The governing motor choice must come from manufacturer torque-speed, power and air-consumption data at the stated inlet pressure.

1. Purpose and Engineering Decision

Air motors are selected by the mechanical work they must deliver at the shaft: speed, torque, starting requirement, duty cycle and allowable operating pressure. A motor cannot be selected correctly from air consumption alone, because two motors can consume similar airflow while producing very different torque-speed characteristics.

The worksheet keeps working torque, starting torque, stall torque and free speed separate.

Selection mode

Primary output

Known torque + speed

Required shaft power and candidate operating point

Known power + speed

Required torque

Starting-duty check

Starting torque margin

Variable-load profile

Normal / peak / start / stall-risk cases

Air-system check

Airflow and inlet pressure required at motor connection

2. Core Mechanical Relationship

P_mech = 2 x pi x n x T / 60

Where P_mech is shaft power in watts, n is rotational speed in revolutions per minute and T is torque in newton-metres. Equivalent rearrangements are:

  • T = 60 x P_mech / (2 x pi x n)
  • n = 60 x P_mech / (2 x pi x T)

These equations are exact for rotational mechanical power when consistent SI units are used.

3. Required Asset - Air Motor Duty Selection Worksheet

Field

Entry / calculation

Selection control

Application / driven machine

User input

Required

Required output speed

rpm

Normal and peak

Required running torque

N.m

At driven shaft

Required starting torque

N.m

If load must start under torque

Peak / breakaway torque

N.m

Separate from normal torque

Required mechanical power

Calculated / entered

Cross-check

Duty cycle

Continuous / intermittent / cyclic

Required

Direction

One-way / reversible

Required

Available inlet pressure

bar(g) / psi(g)

At motor inlet

Allowable pressure drop

bar / psi

Supply path

Candidate motor model

Exact OEM model

Required for final PASS

OEM rated / free speed

rpm

Source curve

OEM torque-speed point

Torque at target speed

Source curve

OEM starting torque

N.m

Source data

OEM stall torque

N.m

Source data

OEM air consumption

L/s, m3/min, cfm

At selected pressure / duty

Decision

PASS / HOLD / FAIL

Reason required

4. Working Point Must Come from the Torque-Speed Curve

Pneumatic motors generally produce different torque at different speeds. The required operating point must therefore be checked on the exact motor's torque-speed curve at the intended supply pressure.

5. Starting Torque, Running Torque and Stall Torque Are Different

Term

Engineering meaning

Running torque

Torque required while the driven machine is operating at the target speed

Starting torque

Torque available from standstill; compare with breakaway/load-start requirement

Peak torque

Short-duration process requirement that may exceed normal running torque

Stall torque

Torque at zero speed; not a recommended continuous operating condition

Free speed

Approximate no-load speed; not the normal loaded operating point

6. Torque Margin

Running Torque Margin = T_motor_at_target_speed - T_required

Starting Torque Margin = T_motor_start - T_required_start

A positive running margin does not prove that the motor can start the load, and a high stall torque does not prove acceptable efficiency or speed stability.

7. Gearbox / Reduction Boundary

If gearing is used between the motor and the driven load, the worksheet may translate shaft duty through the gear ratio and an explicit mechanical efficiency.

n_motor = n_load x Gear Ratio

T_motor_required = T_load / (Gear Ratio x eta_gear)

Gearbox efficiency must be entered from a defensible source or shown as an explicit preliminary assumption.

8. Available Pressure Is Pressure at the Motor

Motor performance should be checked at the pressure actually available at the motor inlet while air is flowing. Compressor discharge pressure can be higher than motor inlet pressure because of dryers, filters, regulators, valves, piping, hoses and couplings.

9. Air Consumption Must Be Model-Specific

Air consumption is not calculated from shaft power alone. Pneumatic-motor efficiency and internal flow characteristics vary by design and operating point.

10. Mechanical Efficiency Check

eta_overall = P_mechanical_out / P_pneumatic_input

Where pneumatic input power is available from a verified thermodynamic calculation or OEM data, an efficiency screen may be shown.

11. Worked Validation Case A - Torque and Speed to Power

Synthetic validation case: a mixer requires 18 N.m at 900 rpm during normal operation.

P = 2 x pi x 900 x 18 / 60 = 1.70 kW

The required mechanical shaft power is approximately 1.70 kW. The candidate motor must still be checked for at least 18 N.m at 900 rpm on its OEM curve.

12. Worked Validation Case B - Power and Speed to Torque

Synthetic validation case: the driven load requires 2.2 kW at 1,200 rpm.

T = 60 x 2200 / (2 x pi x 1200) = 17.51 N.m

Required running torque is approximately 17.51 N.m at 1,200 rpm.

13. Worked Validation Case C - Gear Reduction

Synthetic validation case: load requires 40 N.m at 300 rpm. A 3:1 reduction gearbox is proposed with a documented efficiency of 0.92.

Calculated item

Result

Motor speed

900 rpm

Motor torque required

14.49 N.m

Load mechanical power

1.26 kW

Motor mechanical output before gearbox losses

1.37 kW

14. Worked Validation Case D - Starting Torque Gate

Synthetic validation case: required normal running torque is 12 N.m, but the machine needs 24 N.m breakaway torque at start. Candidate Motor A provides 16 N.m starting torque; Candidate Motor B provides 28 N.m.

Candidate

Running duty

Starting duty

Decision

Motor A

May satisfy running curve

16 < 24 N.m

FAIL start duty

Motor B

Check running curve separately

28 > 24 N.m

Starting duty PASS

This case shows why normal power alone is not enough. Starting torque can govern the motor size.

15. Duty Cycle and Thermal / Wear Considerations

Continuous, intermittent and frequent-start duties may require different motor sizing and lubrication arrangements.

16. Reversing Duty

Reversible air motors may be attractive for winches, positioning and maintenance equipment, but direction changes can create transient torque and control demands. The worksheet therefore records reversal frequency and whether the load can reverse under torque.

17. Speed Control

Air-motor speed may be influenced by inlet pressure, throttling, flow control and load. Where speed accuracy matters, the control method and feedback requirement should be stated.

18. Supply-Air Quality

Motor OEM requirements should govern filtration and lubrication. The broader compressed-air source material reinforces the point-of-use principle: filter where necessary, regulate intelligently, and lubricate only where specified.

19. Multiple Motor Demand

Q_total = Sum(Q_motor,i x Simultaneity_i)

Each motor's air consumption should come from its own model-specific operating point. Plant demand then depends on how many motors can operate simultaneously and for how long.

20. Input Model

Input group

Field

Validation

Load

Speed rpm

> 0 for running case

Load

Running torque N.m

>= 0

Load

Starting / breakaway torque

Optional but required when start under load matters

Load

Peak torque

Optional

Transmission

Gear ratio

> 0 if used

Transmission

Efficiency

0 < eta <= 1

Air

Available motor inlet pressure

Basis required

Air

OEM air consumption

Model-specific

Duty

Continuous/intermittent/cyclic

Required

Control

Direction / reversal / speed regulation

Required

Evidence

OEM curve/table revision

Required for final PASS

21. Validation and Guardrails

Condition

Required behaviour

Target speed <= 0 for running case

Block calculation

Negative torque

Block calculation

Gear ratio <= 0

Block calculation

Gear efficiency outside 0-1

Block calculation

OEM curve missing

HOLD final selection

Air consumption borrowed from another model

HOLD

Compressor pressure used instead of motor inlet pressure

Warn / require pressure budget

Stall torque used as continuous working torque

Block PASS

Free speed used as loaded operating speed

Warn

Catalogue generic air-tool consumption treated as motor rating

Block final selection

22. PASS / HOLD / FAIL Logic

Status

Meaning

PASS

Target speed/torque, starting duty and air supply are covered by model-specific OEM data

HOLD

One or more governing inputs or OEM curves are missing/unverified

FAIL

Candidate cannot meet running torque, starting torque, speed or air-supply requirement

Related pages

Talk to Reddy Compressors

Tell us the job. We will send the right answer.

Buying, hiring, servicing or looking for a part: share what the air must run, the pressure and the site. A nameplate photo is often enough to start.

+91 99590 60718+91 92468 88812