Open resourceMeasure the energy. Identify the source. Keep the carbon calculation traceable.
A compressed-air carbon calculation starts with the energy actually used to provide the air service, not the compressor's motor rating. Record the reporting period, included equipment, electricity and fuel sources, and the emission factor applicable to each source. Calculate each line separately, then combine only results that use compatible boundaries and gas coverage. Keep measured energy, estimated energy, location-based results, market-based results and project savings distinguishable. [S2, S3, R1]
This page provides an editable carbon-accounting worksheet for compressor packages, air treatment and associated utilities. Its purpose is to make an operational calculation reproducible: another reviewer should be able to follow each result back to a meter, an allocation, an emission-factor record and a stated period. The examples are fictional teaching datasets; none is a Reddy Compressors customer result, current tariff, official emission factor or assurance statement.
1. The decision this worksheet supports
It is not a compressor-sizing tool, a product lifecycle assessment or a carbon-credit calculator.
Use the result to identify missing meters, compare like-for-like operating periods, allocate shared utility emissions and support a documented improvement programme. A compressor-room subtotal remains part of the facility inventory. It must not be added to a facility electricity total that already includes the same equipment.
The worksheet produces an energy ledger, a factor register, separate emissions results by source and method, optional intensity indicators, and an explanation of exclusions. A defensible output can be a qualified estimate. An unexplained precise number is not preferable to a transparent estimate with visible gaps.
2. Define the physical boundary before entering numbers
Draw the boundary around the service being assessed. A compressor-package calculation may stop at the package feeder. A station calculation may include separate dryers, cooling-water pumps, ventilation fans, drain controls and sequencing equipment. A delivered-air calculation also needs an agreed air-delivery measurement point.
Record included assets by tag rather than by a loose description such as “compressor electricity.” Identify meters that contain other meters. When a station incomer includes compressor feeders and a dryer feeder, use the incomer as the total and the downstream meters for reconciliation; do not add all three levels together.
Boundary item | Worksheet treatment | Typical error to prevent |
|---|---|---|
Compressor package | Include the package supply once | Adding the motor again inside package kWh |
Separate dryer and auxiliaries | Include where inside the selected boundary | Omitting heaters, fans or cooling pumps |
Shared cooling or ventilation | Allocate with a documented driver | Charging the entire shared plant to air |
Temporary compressor or generator | Keep a separate dated source line | Applying a grid factor to diesel consumption |
Delivered compressed air | Record volume reference and delivery point | Mixing inlet flow with downstream delivered volume |
3. Separate the engineering subtotal from corporate scopes
An engineering boundary describes equipment and service. An organisational boundary determines whose emissions are reported. Under the GHG Protocol framework, purchased electricity consumption is associated with Scope 2; fuel combustion and refrigerant releases from owned or controlled equipment can fall in Scope 1. Upstream fuel and electricity-related activities require separate Scope 3 treatment where applicable. [R1, R2, R3]
A diesel rental unit is not assigned a scope solely because it is rented. The customer and supplier must establish the relevant control, lease and service arrangement. Likewise, an outsourced compressed-air supply requires its contract and organisational boundary to be assessed rather than an automatic classification from the invoice description.
This worksheet does not establish a complete corporate inventory. A limited electricity-only calculation should be labelled exactly that. Where refrigerant losses, fuel combustion or other relevant sources are outside the chosen assessment, disclose the exclusion instead of presenting the subtotal as the entire air system's footprint.
4. Build a source-by-source activity ledger
Create one row for each distinct combination of source, period, boundary, gas basis and calculation method. A single compressor can have grid-electricity rows, generator-supplied electricity allocations and a separate treatment allocation without changing its asset identity. Preserve these distinctions before aggregation.
At minimum, record asset or meter ID, start and end timestamps, source type, original quantity and units, meter multiplier, evidence reference, allocation share and estimate flag. Keep original readings beside processed quantities. Meter resets, rollovers and replacements need their own notes so a negative difference is not silently accepted as consumption.
Close the ledger against available station and facility records. An unexplained difference is a reconciliation item, not an automatic leak estimate. Billing periods, feeder coverage, standby loads, transformer losses and estimated invoices can all cause differences.
5. Convert electrical records into period energy
For cumulative meters, period energy is the end reading minus the start reading, after documented multiplier and reset treatment. For interval data, sum the interval kWh. When only representative real-power states are available, use a time-weighted estimate:
E = Σ(Pi × hi)
Here E is energy in kWh, Pi is average real input power in kW during state i, and hi is the duration in hours. Intervals for the same asset must not overlap. If the logger contains average kW rather than kWh, multiply each value by its actual interval duration. Missing intervals are not zero-consumption intervals.
Retain loaded, unloaded, stopped-but-energised and part-load states when they materially affect the estimate. Do not multiply rated motor kW by annual operating hours and call it measured consumption. Current alone is not real power, and a VSD output measurement is not automatically comparable with a package supply measurement.
Power-factor correction or a lower electricity bill does not, by itself, establish reduced kWh. Carbon activity follows energy consumption, while charges may also change because of demand, tariffs and billing adjustments.
6. Give every emission factor its own identity
A factor is more than a decimal. Store its publisher, document or dataset title, release/version, table or record identifier, activity year, geography, units, included gases, calculation boundary, accounting method and retrieval date. Record the person or role approving its applicability. Keep the original source file or stable reference with the calculation.
Distinguish the year in which a factor was published from the year of electricity generation that it describes. A recently downloaded historic factor remains historic. An available factor can be used provisionally when appropriate, but its age and the reason for selecting it must remain visible.
Factor field | Required detail |
|---|---|
Factor ID and value | Unique ID; original and converted value |
Activity denominator | kWh, MWh, litre, kg fuel or another declared unit |
Gas coverage | CO2 only, named individual gases, or defined CO2e coverage |
Method and boundary | Grid average, supplier/product, residual mix, combustion or lifecycle |
Geography and activity year | The grid, market, fuel or region represented |
Provenance | Publisher, version, exact record, retrieval date and approval |
A factor copied from a marketing page without its original basis is a research lead, not an approved calculation input.
7. Selecting an electricity factor for an Indian site
For an Indian grid-connected installation, consult the Central Electricity Authority's official CO2 database and the reporting method applicable to the organisation. The CEA guide distinguishes weighted-average, operating-margin, build-margin and combined-margin factors; these represent different calculations and are not interchangeable. Preserve the selected series, treatment of renewable generation and cross-border transfers, and year. [R4]
The existence of a factor in a carbon-project database does not make every factor in that database suitable for a corporate electricity inventory. Select a factor that fits the intended inventory or project calculation. Keep any project-baseline factor in a separate field from the inventory factor.
Where the selected record is expressed in tCO2/MWh, its numerical value is the same in kgCO2/kWh: both numerator and denominator change by 1,000. The gas label remains CO2. Do not relabel a CO2-only result as a complete greenhouse-gas total, or add unsupported methane and nitrous-oxide allowances.
8. Core carbon equations and unit controls
For an electricity row using a factor in kg of the stated gas basis per kWh:
- Ckg = E(kWh) × EF(kg/kWh)
- Ct = Ckg ÷ 1,000
For several rows, calculate C for each row before summing compatible results. Multiplication by a dimensionally compatible factor is the common activity-based calculation approach; factor boundaries still determine what the answer represents. [R3]
For fuel entered in litres, use a factor per litre for the identified fuel and declared combustion or lifecycle boundary. A factor per kilogram requires a documented density conversion. A factor per unit of energy requires the correct heating-value basis. Do not mix gross and net calorific values without conversion.
A factor already expressed in CO2e incorporates its stated greenhouse-gas treatment; do not apply global-warming potentials again. When calculating individual gases, retain each gas mass and the selected global-warming-potential source before conversion. Store full numerical precision in the worksheet and round only displayed outputs.
9. Location-based and market-based electricity views
Location-based reporting uses the relevant grid-average basis. Market-based reporting uses qualifying contractual or supplier information and the appropriate treatment of unmatched electricity. The 2015 Scope 2 Guidance provides factor hierarchies and quality criteria for contractual instruments, and requires dual reporting in the circumstances it specifies. The two results describe alternative accounting views of electricity; they are not additive. [R1]
Within the market-based panel, every quantity must be assigned to a valid factor or a documented fallback. Record certificate or contract identity, quantity, period, market and evidence of exclusive allocation or retirement as relevant. A procurement label alone is insufficient.
Do not subtract certificate-associated kWh from physical electricity consumption. If 390,000 kWh was consumed, it remains 390,000 kWh in the activity ledger even when some consumption has a different market-based factor. Keep exported electricity separate, and review energy-attribute ownership before making claims about onsite renewable supply. [R1]
10. Grid, generator and direct-diesel operation
Use separate source lines when the air service operates on different energy sources. For a direct-diesel compressor, fuel records are the activity basis for combustion emissions. For an electric compressor supplied by an onsite generator, calculate generator emissions at the generation boundary and allocate an appropriate share to the compressed-air service.
An internal allocation may use metered compressor kWh divided by total metered useful electricity delivered from that generator over the same period, provided the chosen method also explains auxiliary and distribution losses. This is a management allocation, not a universal fuel-consumption curve. A partly loaded generator's actual fuel use should not be reconstructed from compressor motor rating alone.
Do not calculate both the allocated generator fuel emissions and a grid-factor charge on the same generator-supplied kWh. Equally, do not add the compressor's allocated fuel share on top of a facility fuel total that already includes it. Preserve both the generator total and allocation so the facility can consolidate correctly.
11. Dryers, purge, leaks and heat recovery
Separate direct electrical consumption from air demand that creates additional compressor work. A heated dryer may consume heater and blower electricity as well as purge air. A heatless dryer may have low direct electricity use but still consume compressed air. Measure the station electricity boundary first, then use component estimates to explain it—not to charge the same energy twice. [S2, R5]
The energy used to produce leaked or purged air is already inside a complete station kWh measurement. A calculated “leak carbon” figure is a diagnostic allocation within that total. Add it only when constructing a genuinely disjoint bottom-up model. Repairing a leak does not establish a fixed kWh saving without considering compressor control response and the measured post-repair duty. [R5]
Heat-recovery benefits belong in a separately described comparison with the displaced heating source. Record useful delivered heat, the receiving process, displacement evidence and additional pump or fan electricity. Do not deduct theoretical recovered heat from compressor electrical input.
12. Allocate shared emissions and define useful intensity
For comparable service at a common header, a transparent internal allocation can use each user's measured reference-volume share. Define aj = Vj / ΣVj, then allocate Cj = aj × Cshared. This is a worksheet convention, not a claim that every cubic metre physically required the same marginal energy.
Different pressure levels, treatment classes, boosters or dedicated drying can make a simple volume allocation misleading. Allocate dedicated equipment directly first, then distribute only the genuinely shared pool. Keep unmetered users and balance differences visible as common or unallocated amounts; do not distribute an unexplained residual merely to make every department look complete.
Specific electricity = E / Vref, in kWh per reference m3.
Carbon intensity = Ckg / Vref, in kg of the declared gas basis per reference m3.
State reference temperature, absolute pressure and moisture convention. Do not assume that all “normal,” “standard,” FAD and actual-volume readings are identical. Keep process service pressure and air-quality requirements beside the intensity, and compare only aligned time and delivery boundaries.
13. Keep reporting periods and revisions reproducible
Specify calendar year, financial year, month or project window explicitly. Meter intervals should be clipped or apportioned to that window using a declared method. Where a bill spans two periods, use interval data where available; a day-count allocation is an estimate and should be labelled accordingly.
Use separate rows when the applicable factors or supply sources change during the period. Do not replace the factor in a historic record with a newly released factor without preserving the original result and explaining the revision. The organisation's inventory policy determines when formal restatement is needed; the worksheet preserves both versions.
A closed reporting record should contain the raw activity, original factor, calculation version, approval date and exclusions. Later corrections produce a revised record. They should not silently overwrite the explanation behind an earlier report or customer communication.
14. Separate energy improvement from emission-factor change
A lower reported carbon total can result from lower output, better energy performance, a changed electricity factor, a procurement change or a moved reporting boundary. The carbon ledger alone does not establish which mechanism caused the change. Use the supplied measurement-and-verification approach to compare operating conditions.
For a single compatible factor and an unchanged boundary, an exact two-step bridge is:
C0 − C1 = (E0 − E1) × EF0 + E1 × (EF0 − EF1)
The first term is the energy-quantity effect evaluated at the initial factor. The second is the factor effect evaluated at final energy. This is an arithmetic decomposition, not proof that all energy reduction came from a particular project. State this ordering because another valid decomposition can allocate the interaction differently.
For project assessment, calculate adjusted baseline energy for the post-project duty and compare it with actual post-project energy. Use a common comparison factor when isolating energy performance, and report the resulting estimate separately from the period inventory. Do not add the two as independent benefits.
15. Missing data, uncertainty and practical confidence
Mark each activity line measured, allocated, modelled or assumed. Keep the proportion of estimated electricity visible. A factor can be documented while the activity data remain weak; a good meter does not rescue an unsuitable factor. Data quality should therefore be assessed separately for measurement, allocation, factor applicability and reporting completeness.
Missing activity or factor data should produce “not calculated” for the affected line, not zero emissions. Show any calculated subtotal together with the unquantified sources. A sensitivity interval can demonstrate the effect of alternative assumptions, but do not label it a statistical confidence interval unless its statistical basis is established.
For example, a hypothetical 390,000 kWh estimate with a ±2% activity scenario and a factor scenario of 0.65–0.75 kgCO2e/kWh gives 248.43–298.35 tCO2e by multiplying the paired lower and upper inputs. Those limits describe the chosen scenarios; they do not establish a probability that actual emissions lie within them.
16. Worked case A — Station energy, allocation and intensity
Illustrative data only. A plant records 360,000 kWh for compressor packages, 24,000 kWh for separately metered dryers, and 6,000 kWh for dedicated ventilation and cooling auxiliaries. The three readings are non-overlapping. A fictional approved teaching factor is 0.700 kgCO2e/kWh. All quantities cover the same year.
Calculation | Working | Result |
|---|---|---|
Station electricity | 360,000 + 24,000 + 6,000 | 390,000 kWh |
Electricity-related emissions | 390,000 × 0.700 / 1,000 | 273.00 tCO2e |
Delivered reference volume | Declared meter total | 1,200,000 reference m3 |
Specific electricity | 390,000 / 1,200,000 | 0.325 kWh/reference m3 |
Carbon intensity | 273,000 / 1,200,000 | 0.2275 kgCO2e/reference m3 |
For this example only, volume means dry air at 20°C and 1.01325 bar absolute; delivered service pressure is documented separately. Department A uses 720,000 reference m3 and B uses 360,000. The remaining 120,000 is identified as common service and unallocated balance, not automatically as leakage.
A receives 60% of the shared emissions, or 163.80 tCO2e; B receives 30%, or 81.90 tCO2e; and the common balance retains 27.30 tCO2e. These sum to 273.00 tCO2e. If a separate incomer also reads 390,000 kWh, it confirms the total; adding it would incorrectly double the emissions.
17. Worked case B — Two electricity-accounting views
Illustrative data only. Retain Case A's 390,000 kWh consumption. The hypothetical location-based factor is 0.700 kgCO2e/kWh. For market-based teaching purposes, assume 150,000 kWh is covered by documented qualifying instruments with a zero generation-emissions factor. The remaining 240,000 kWh uses a fictional approved residual factor of 0.800 kgCO2e/kWh.
View or component | Calculation | Result |
|---|---|---|
Location-based electricity total | 390,000 × 0.700 / 1,000 | 273.00 tCO2e |
Market-based matched component | 150,000 × 0 / 1,000 | 0.00 tCO2e |
Market-based unmatched component | 240,000 × 0.800 / 1,000 | 192.00 tCO2e |
Market-based electricity total | 0 + 192.00 | 192.00 tCO2e |
The output is two labelled totals, not 465.00 tCO2e and not a physical consumption of 240,000 kWh. The 81.00 tCO2e difference between views is not evidence that compressor efficiency improved.
If the qualifying-instrument evidence is absent, the zero-factor assignment fails validation. Use the applicable documented fallback and explain it; do not retain an unsupported low total. The numbers in this case are not evidence that a residual mix or certificate type is available for any specific Indian site. Actual eligibility and fallback selection follow the adopted reporting method. [R1]
18. Worked case C — Electricity plus direct-diesel service
Illustrative CO2-only calculation. A temporary project consumes 100,000 kWh of purchased electricity for its electric air equipment and 5,000 litres of diesel in a separately operated direct-diesel compressor. For this example, both sources are within the reporting entity's relevant boundary. Teaching factors are 0.700 kgCO2/kWh and 2.680 kgCO2/litre. Neither is presented as an official current factor.
Electricity-related CO2 is 100,000 × 0.700 / 1,000 = 70.00 tCO2. Diesel-combustion CO2 is 5,000 × 2.680 / 1,000 = 13.40 tCO2. The operational CO2 subtotal is therefore 83.40 tCO2, with the electricity and direct-combustion components retained separately. It is not described as an all-gas CO2e inventory.
A separate generator-allocation illustration uses 2,000 litres for a generator delivering 8,000 useful kWh to several users. Compressed air receives 3,000 kWh. Under the stated output-share convention, its allocated fuel is 2,000 × 3,000 / 8,000 = 750 litres; allocated CO2 is 750 × 2.680 / 1,000 = 2.01 tCO2. This separate illustration is not added to the earlier project subtotal.
The allocation is only as representative as the common period, output meters and treatment of generator losses. It does not imply the generator consumes 0.25 litre/kWh at every operating point.
19. Worked case D — Inventory change versus project benefit
Illustrative data only. Baseline electricity is 600,000 kWh at 0.750 kgCO2e/kWh. The next period uses 480,000 kWh at 0.650 kgCO2e/kWh. The equipment boundary is unchanged. The inventory falls from 450.00 to 312.00 tCO2e: a reduction of 138.00 tCO2e, or 30.67% of the baseline total.
Explanation | Calculation | Contribution |
|---|---|---|
Energy-quantity effect at initial factor | (600,000 − 480,000) × 0.750 / 1,000 | 90.00 tCO2e |
Factor effect at final energy | 480,000 × (0.750 − 0.650) / 1,000 | 48.00 tCO2e |
Reconciled inventory change | 90.00 + 48.00 | 138.00 tCO2e |
Now assume a separately documented production-adjusted baseline model predicts 660,000 kWh for the post-project production duty. Actual consumption remains 480,000 kWh. Estimated avoided electricity is 180,000 kWh. Evaluated at the common comparison factor of 0.650, the project estimate is 117.00 tCO2e.
The 660,000 kWh is a supplied hypothetical model output, not a value calculated automatically from a 10% output increase. The 117.00 tCO2e project estimate and 138.00 tCO2e inventory change answer different questions. Do not add them, call their difference unexplained error, or label either as a tradable carbon credit.
20. Editable worksheet — Boundary and activity records
Copy the following tables for each reporting period. Replace the entry prompts with project information. These Word tables are manually editable; they do not execute calculations automatically. Retain supporting meter exports and factor records outside the public website and use the reference fields to identify them.
Assessment field | Project entry |
|---|---|
Assessment ID / revision | [Enter unique ID and version] |
Site / reporting entity | [Enter site and organisational boundary owner] |
Period / time zone | [Enter start, end and time zone] |
Purpose | [Inventory subtotal / internal allocation / project comparison] |
Physical boundary | [List equipment, meter hierarchy and delivery point] |
Methods / gas basis | [Location-based / market-based / CO2 / defined CO2e] |
Included sources / exclusions | [Electricity, fuel, refrigerant, shared utilities and omissions] |
Evidence owner / reviewer | [Enter names or responsible roles and review date] |
Activity record | Original amount / unit | Allocation and evidence |
|---|---|---|
A01: compressor feeder | [Quantity, unit, period] | [Share; meter ID; multiplier; source file] |
A02: separate air treatment | [Quantity, unit, period] | [Confirm not contained in A01] |
A03: shared utility | [Quantity, unit, period] | [Allocation driver and denominator] |
A04: generator or direct fuel | [Quantity, unit, period] | [Control boundary; fuel specification; records] |
A05: other included source | [Quantity, unit, period] | [Description, evidence and calculation method] |
For every row add measured/allocated/modelled/assumed status, missing-data treatment and an emissions-factor ID. A refrigerant row needs a separate gas-specific mass calculation; it must not be processed as electricity. When the source list grows, duplicate the row structure rather than merging incompatible activities into an undocumented “other” number.
21. Editable worksheet — Factors and results
Use one factor record for each approved source definition, then reference it by ID. Store contractual evidence separately from grid-average references. Public-facing exports should omit confidential invoices, account identifiers and contract attachments while retaining non-sensitive factor provenance.
Factor record | Entry |
|---|---|
F01: publisher / dataset / version | [Enter exact source title and release] |
Record location / activity year / geography | [Table, row, period and represented grid or fuel] |
Original value / units / gas coverage | [Enter exactly as published] |
Normalised value / conversion | [Enter conversion with units] |
Method / included lifecycle stages | [Inventory method and generation/combustion/lifecycle basis] |
Retrieval / approval / expiry review | [Dates, reviewer and reason for applicability] |
Result record | Entry or manual calculation |
|---|---|
Electricity by source | [Sum eligible non-overlapping activity rows in kWh] |
Location-based result | [Σ applicable electricity × location factor / 1,000] |
Market-based result | [Σ matched and unmatched electricity × assigned factors / 1,000] |
Direct combustion or other gases | [Separate results and explicitly stated gas basis] |
Common / unallocated share | [Amount, rationale and outstanding reconciliation] |
Intensity | [Result / aligned reference volume or production denominator] |
Estimates / exclusions / unresolved factors | [Visible limitations; no invented zero values] |
Conclusion / review | [What the result supports, what it does not, reviewer and date] |
22. Turning the result into an engineering action
Begin with the largest well-supported energy contributors and the largest information gaps. High unloaded consumption points toward control and duty investigation. Treatment loads may need regeneration-state and pressure-loss analysis. A growing shared balance may need better metering before a confident departmental comparison is possible. Use the existing measurement, demand-profile and energy pages for the engineering diagnosis rather than expecting a carbon factor to identify a machine fault.
Assign each improvement an owner, implementation date, expected energy effect and verification boundary. Keep service pressure, air quality and continuity requirements intact. A lower carbon result achieved by failing to provide the required air service is not a successful engineering outcome.
Close an action with the observed energy result, reporting factor and remaining limitations.
23. Questions plant teams ask
Does an electric compressor have zero emissions because it has no exhaust? Its operation still uses electricity. Record the associated electricity-generation emissions under the selected method rather than relying on the absence of onsite exhaust. [R1]
Can motor kW multiplied by hours be used? Only as a labelled screening estimate when better evidence is unavailable. Metered kWh or time-weighted real input power is preferable.
Should dryers and ventilation be included? Include them when they are within the declared system boundary, and check that their energy is not already contained in another meter.
Are CO2 and CO2e interchangeable labels? No. Preserve the gas coverage of the factor and calculation. A CO2-only factor must not be presented as a complete all-gas result.
Can the same factor be used for every year? A fixed factor can support a clearly labelled constant-factor performance comparison. Period inventories need the factor selection required by their reporting method, with year and version recorded.
Does a renewable certificate reduce measured kWh? No. Procurement evidence can affect an eligible accounting result; it does not change the meter record. [R1]
Should estimated leak emissions be added to station emissions? Not when the station meter already includes the energy used to supply those leaks. Show leak-related estimates as a diagnostic allocation instead.
What happens when a factor is missing? Retain the activity and mark its emissions uncalculated. Display a partial subtotal only with the missing source clearly identified.
Can carbon be allocated per cubic metre of air? Yes as a declared internal allocation when volume, pressure, treatment and time boundaries are suitable. It is not automatically a product footprint or a marginal-energy prediction.
Does this worksheet verify a carbon-neutral claim? No. It supports an operational calculation and evidence trail; it does not certify neutrality, assure an inventory or create emission-reduction credits.
Primary enquiry: Request a Compressed-Air Energy and Carbon Assessment. Provide the period, asset list, meter records, electricity-source information and any required reporting method. Do not upload confidential credentials or unrelated personal records.
IMPLEMENTATION AND SOURCE NOTES — NOT PUBLIC ARTICLE COPY
25. Input safeguards and expected-result tests
Reject non-finite numbers, negative consumption without an explicit correction record, negative factors in ordinary inventory mode, invalid periods, overlapping duplicate records, and allocations outside 0–100%. A zero factor is allowed only with a stated basis and evidence status. A zero denominator blocks intensity calculation without deleting the emissions subtotal.
Test | Expected behaviour |
|---|---|
100,000 kWh × 0.700 kgCO2/kWh | 70,000 kgCO2; 70.00 tCO2 |
100 MWh × 0.700 tCO2/MWh | Same 70.00 tCO2 result |
Case A disjoint energy rows | 390,000 kWh and 273.00 tCO2e |
Add a station incomer containing Case A feeders | Block double inclusion; permit reconciliation use |
Case B two methods | Show 273.00 and 192.00 separately; never sum |
Contract covers 400,000 of 390,000 kWh | Reject excess consumption allocation |
Missing factor for a nonzero activity | Mark uncalculated; subtotal clearly incomplete |
CO2-only and CO2e records | No unqualified all-gas total; require compatible basis |
Missing air volume or volume equals zero | Emissions retained; intensity not calculated |
Case C generator share | 750 litres allocated; 2.01 tCO2 |
Case D change bridge | 90.00 + 48.00 = 138.00 tCO2e |
Case D adjusted project estimate | 117.00 tCO2e; separate from inventory change |
Case A allocation percentages | 60% + 30% + 10% = 100%; total reconciles |
Missing interval in logger | Flag gap; do not replace with zero automatically |
These are expected-result specifications, not evidence that a website calculator has executed the tests.
26. Website interface, exports and accessibility
Provide a simple assessment flow: boundary, energy records, factors, optional allocation, results and export. Offer a clearly marked demonstration dataset separately from an empty project worksheet. Loading a demonstration must visibly label every resulting page “Illustrative example”; clearing it must remove its factors as well as its activity values.
Show energy and emissions alongside the period, method and gas basis. Use separate location-based and market-based cards. Put unresolved-source warnings beside the subtotal, not only in a collapsed help panel. Allow users to inspect the equation and source record behind each number.
Use associated form labels, descriptive error messages, keyboard-operable controls and screen-reader announcements after recalculation. Status must not depend on colour alone. On mobile, show compact record cards and keep wide tables locally scrollable. Exports must retain method labels, exclusions and factor provenance; a screenshot of one number is not an adequate assessment record.
Client-side calculation must not silently send plant data to analytics or third parties. Any server submission requires an explicit purpose, suitable access control and a stated retention process. The assessment enquiry and file-upload path need their own implementation tests before launch.