Air Demand Duration Curve Tool

6 min read11 sections

Interactive resource

Use the working tool for this page

This page has a matching worksheet, calculator or comparison resource. It runs in your browser: enter your own measured values and keep the evidence behind every result.

Open resource

It preserves data coverage, missing intervals and measurement basis so the curve can support capacity, trim, fleet, rental and energy decisions without disguising gaps as real demand.

1. Purpose and Engineering Decision

A chronological trend answers when demand changed. A duration curve answers how often high, medium and low demand occurred. This separates short peaks from persistent base demand and exposes the portion of the operating year that occupies each demand band.

The tool is useful for compressor-capacity review, base/trim selection, fleet-dispatch studies, peak-rental planning, storage screening and energy modelling. It must not be used to infer chronology, event sequence or recovery time; those remain properties of the original time-series data.

Decision

Capacity screen

Hours demand exceeds a selected flow threshold

Base / trim review

Exceedance demand levels such as E10, E50 and E90

Peak-duty review

Robust peak metrics plus maximum observed value

Fleet analysis

Rental / temporary-air review

Hours above permanent plant capacity

Data-quality review

Valid hours, missing hours, gap register and coverage %

2. Required Asset - Duration Curve Generator and Missing Data Rules

The curve cannot be considered complete unless the user can see how much of the scheduled period was actually represented by valid data.

Required asset

Minimum function

Duration Curve Generator

Sort valid demand points descending, preserve time weight, calculate cumulative hours and exceedance %

Missing Data Rules

Detect gaps, classify missing intervals, prevent silent filling and report coverage

Import Audit

Accepted rows, rejected rows, duplicates, invalid timestamps, negative/invalid flows

Basis Register

Flow unit/reference basis, timezone, sampling interval, pressure band if used

Export

Duration table + summary metrics + gap register + assumptions

3. Data Input Model

Field

Requirement / note

Timestamp

Required; parse to one declared timezone

Demand flow

Flow unit

m3/min, m3/h, cfm or selected common basis

Pressure

Optional but valuable for separating pressure-duty bands

Compressor state

Optional; useful for distinguishing intentional zero from missing signal

Package kW

Optional; enables demand-power pairing for later energy tools

Quality flag

Good / suspect / invalid / manually excluded

Source

Flow meter, controller, estimator or imported historian tag

4. Time Weighting

Duration curves must represent time, not row count. For regularly sampled data, each valid record receives the sampling interval as its time weight. For irregular data, the tool assigns each point a valid interval only up to the configured maximum gap threshold.

Weight_i = Valid Time represented by sample i

T_valid = Sum(Weight_i)

If a timestamp-to-next-timestamp interval exceeds the maximum allowed gap, the excess interval is recorded as missing rather than credited to the preceding measurement. This prevents a stale value from being carried across an instrumentation outage.

5. Missing-Data Rules

Condition

Single missing sample inside otherwise regular data

Mark gap; no silent interpolation

Short gap below user-approved imputation limit

May be filled only if user selects method and tool records imputed hours

Long gap

Remain missing; exclude from observed duration curve

Duplicate timestamp

Keep one according to explicit duplicate rule; report duplicate count

Zero flow with healthy meter / confirmed stopped plant

Treat as valid zero demand

Zero flow during sensor fault / communication loss

Treat as missing, not demand

Negative flow where impossible

Invalid; exclude and report

Outlier / spike

Retain by default with flag; do not auto-delete

Manual exclusion

Preserve original row and reason in audit trail

Recommended imputation choices are none, forward-hold for very short stable gaps, or linear interpolation for short gaps where the user explicitly accepts the assumption. The tool must never interpolate across a known plant start/stop, shift boundary, compressor trip or major process transition without explicit user action.

6. Coverage Metrics

Coverage (%) = Valid Observed Time / Scheduled Analysis Time x 100

Missing Time = Scheduled Analysis Time - Valid Observed Time

The primary duration curve uses valid observed time as its denominator. If the user elects an imputation method, an additional imputed-coverage figure is shown separately rather than overwriting the raw coverage result.

Metric

Meaning

Scheduled hours

Full requested analysis window

Valid observed hours

Directly represented by accepted measurements

Imputed hours

Filled only by an explicit user-selected method

Missing hours

Not represented by valid or accepted imputed data

Raw coverage %

Valid observed / scheduled

Effective coverage %

(valid + imputed) / scheduled, clearly labelled

7. Duration Curve Construction

Each accepted flow value is paired with its time weight. The engine sorts pairs by demand from highest to lowest, then accumulates hours. Equal demand values may be grouped to reduce output size without changing total represented time.

Cumulative Hours_j = Sum(Weight_i for all Q_i >= Q_j)

Exceedance_j (%) = Cumulative Hours_j / T_valid x 100

The x-axis therefore represents hours or percent of valid observed time for which demand was equaled or exceeded; the y-axis represents demand flow on the declared reference basis.

8. Exceedance Demand Metrics

Metric

Interpretation

Q_E1

Demand equaled/exceeded for 1% of valid time - robust high-demand indicator

Q_E10

Demand equaled/exceeded for 10% of valid time

Q_E50

Median exceedance demand

Q_E90

Demand equaled/exceeded for 90% of valid time - low/base-demand indicator

Q_max

Maximum accepted observation; sensitive to single spikes

Q_mean

Time-weighted average demand

The tool should use the E-prefix to avoid confusion with statistical percentile naming conventions.

9. Demand Volume and Mean Flow

Total Reference Volume = Sum(Q_i x Weight_i)

Q_mean = Total Reference Volume / T_valid

When Q is in m3/min and time is in minutes, the integrated result is m3 on the same reference basis. The calculator should convert time units internally so that volume integration remains dimensionally correct.

10. Load Factor and Peak Definition

Load Factor = Q_mean / Q_peak_basis

The user chooses the peak basis: maximum observation, Q_E1, Q_E5 or another declared exceedance level. Using a robust peak metric can prevent one isolated meter spike from making the load factor appear artificially low. The selected peak definition must be printed with the result.

11. Reference Test Case A - Regular 15-Minute Data

Assume eight valid 15-minute readings: 40, 35, 30, 30, 25, 20, 15 and 5 m3/min. Total valid time is 2 hours. The sorted sequence is already descending.

Demand m3/min

Cumulative h

Time equaled/exceeded

40

0.25

12.5%

35

0.50

25.0%

30

0.75

37.5%

30

1.00

50.0%

25

1.25

62.5%

20

1.50

75.0%

15

1.75

87.5%

5

2.00

100.0%

Time-weighted average demand is 25.0 m3/min. The maximum 40 m3/min occurs for only 0.25 h, while demand of at least 20 m3/min persists for 1.50 h.

12. Reference Test Case B - Missing Interval

A 24-hour analysis window contains 22.5 hours of valid observations, 0.5 hour of explicitly accepted short-gap interpolation and 1.0 hour of unresolved missing data.

Coverage item

Result

Scheduled period

24.0 h

Valid observed

22.5 h

Imputed

0.5 h

Missing

1.0 h

Raw coverage

93.8%

Effective coverage

95.8%

The raw duration curve is based on 22.5 observed hours.

13. Reference Test Case C - Capacity Exceedance Hours

A plant has 6,000 valid annual operating hours. Its duration curve shows demand above 55 m3/min for 240 hours and above 45 m3/min for 1,050 hours.

Threshold

Hours exceeded

Share of valid time

55 m3/min

240 h

4.0%

45 m3/min

1,050 h

17.5%

This information can support decisions such as whether permanent capacity should cover the full peak, whether a trim machine is justified, or whether short seasonal peaks could be handled by temporary capacity.

14. Reference Test Case D - Robust Peak vs Single Spike

A dataset contains one isolated 85 m3/min point, while Q_E1 is 63 m3/min and mean demand is 38 m3/min.

Peak basis

Load factor

Maximum 85 m3/min

0.447

Q_E1 = 63 m3/min

0.603

15. Demand Bands for Fleet and Energy Analysis

Band example

Output

0-20 m3/min

Hours + mean flow

20-40 m3/min

Hours + mean flow

40-60 m3/min

Hours + mean flow

>60 m3/min

Hours + mean flow

Band boundaries are user inputs or imported from compressor operating envelopes. They should not be hard-coded.

16. Pressure and Quality Segmentation

Where the plant operates multiple pressure or air-quality systems, a single combined duration curve can be misleading.

Segmentation

Reason

Pressure band

High-pressure demand should not automatically be added to lower-pressure capacity

Area / meter

Identifies persistent local demand

Shift / production mode

Separates weekday, weekend, campaign or batch behaviour

Air-quality zone

Prevents ordinary service-air demand from distorting critical-quality system sizing

17. Chronology Warning

Sorting destroys the original order of events. Two plants can have the same duration curve but very different transient behaviour.

18. Data Quality and Outlier Review

Check

Required behaviour

Flatline sensor

Flag long repeated-value runs for review

Step change after meter replacement

Flag basis/calibration change

Unrealistic spike

Retain with suspect flag unless user excludes

Timestamp reversal

Reject or sort only after duplicate/order audit

Unit change mid-file

Block combined curve until normalized

Reference-condition change

Pressure-setpoint change

Allow segmented analysis

19. Input Validation and Guardrails

Condition

Required behaviour

No valid timestamps

Block calculation

No valid flow values

Block calculation

Coverage below user threshold

Generate only with prominent low-coverage warning

Unknown sampling interval in row-count mode

Require timestamps or explicit interval

Irregular gap above threshold

Record missing; do not extend preceding value

Negative flow where unsupported

Exclude + audit

Mixed flow bases

Duplicate timestamps unresolved

Block final curve

More than configured record limit

Aggregate safely while preserving time weights

20. Output Specification

Output

Display rule

Duration curve

Demand vs exceedance hours / %

Coverage summary

Scheduled, valid, imputed and missing hours

Exceedance metrics

Q_E1, Q_E10, Q_E50, Q_E90 + user-selected levels

Mean / integrated volume

Time-weighted

Peak metrics

Maximum plus selected robust peak

Threshold hours

Hours above user-entered capacity levels

Demand bands

Hours + mean flow per band

Gap register

Start, end, duration, treatment

Confidence / warnings

Always visible

Related pages