Construction sites, new factories waiting for their power connection, borewell and pipeline projects, and plants with unreliable grid supply all run electric compressors on diesel generators. It works well when the two machines are matched. When they are not, the compressor fails to start, the generator’s voltage collapses, contactors chatter, the compressor’s controller faults, or the VSD trips on under-voltage. Reddy Compressors and Reddy Generators work under the same management, so we size both sides of the connection together.
Why starting decides the generator size
An induction motor draws several times its full-load current while it accelerates. On the grid this is absorbed easily. A generator, however, has a limited ability to supply a sudden current surge: its voltage dips, and if the dip is deep enough the motor cannot accelerate, contactors drop out and other loads on the same set are disturbed. A screw compressor normally starts unloaded, which helps, but the motor still has to accelerate its own rotor, the coupling and the compressor element.
Rule of practice. A generator sized only for the compressor’s running kVA will usually fail to start it direct-on-line. The starting method is the first question to ask.
Starting methods compared
| Starting method | Starting current (× full-load current) | Planning size (generator kVA per motor kW) | Notes |
|---|---|---|---|
| Direct-on-line (DOL) | About 6–8 × | About 3.0 × | Simple and robust; common on small piston units |
| Star-delta | About 2–3 × (one third of DOL), with a short spike at changeover | About 2.0 × | Standard on most fixed-speed screw compressors above about 7.5 kW |
| Soft starter | About 3–4 ×, ramped | About 1.75 × | Smooth start; ramp time can be set for the generator |
| Variable speed drive (VSD) | About 1–1.5 × | About 1.5 × | Lowest starting surge; the drive’s harmonics need generator margin |
The planning multipliers assume a modern brushless generator with a good automatic voltage regulator and a voltage dip of roughly 15–20% during starting. They are a starting point for selection, not a substitute for the generator maker’s motor-starting curve.
Worked generator sizes
The table uses one method throughout: running kVA is the motor kW divided by an efficiency of 0.92 and a power factor of 0.85; the starting requirement is the planning multiplier × motor kW; the running requirement is the running kVA ÷ 0.8; the larger of the two decides the generator, rounded up to the next common generator size.
| Compressor motor | Running kVA | DOL | Star-delta | Soft starter | VSD |
|---|---|---|---|---|---|
| 22 kW (30 hp) | 28.1 | 66.0 → 82.5 kVA | 44.0 → 62.5 kVA | 38.5 → 40 kVA | 35.2 → 40 kVA |
| 37 kW (50 hp) | 47.3 | 111.0 → 125 kVA | 74.0 → 82.5 kVA | 64.8 → 82.5 kVA | 59.1 → 62.5 kVA |
| 55 kW (75 hp) | 70.3 | 165.0 → 180 kVA | 110.0 → 125 kVA | 96.2 → 100 kVA | 87.9 → 100 kVA |
| 75 kW (100 hp) | 95.9 | 225.0 → 250 kVA | 150.0 → 160 kVA | 131.2 → 160 kVA | 119.9 → 125 kVA |
Where the VSD figure and the running figure are close, the running requirement (running kVA ÷ 0.8) is what decides the size. That is the case for every VSD row above.
Variable speed drives on generators
A VSD compressor is the easiest to start on a generator, but it brings its own checks:
- Harmonics. The drive’s rectifier draws current in pulses. These distort the generator’s voltage waveform, heat the alternator and can upset the automatic voltage regulator. Generator margin (the 1.5 × allowance), a drive with a DC choke or line reactor, and a permanent-magnet or auxiliary-winding excitation system all help.
- Voltage and frequency stability. Drives trip on under-voltage and some on frequency swings. The engine governor must hold frequency when the compressor loads and unloads.
- Light-load running. A large generator running a small load for long hours suffers wet stacking. Do not oversize so far that the set idles most of the day.
- Maker’s requirements. Read the compressor maker’s data on generator supply; some state a minimum kVA-to-kW ratio for their drives.
Count the whole site load
The compressor is rarely alone. Add everything that runs at the same time:
- Refrigerated air dryer: compressor, fan and controls.
- Compressor cooling fan motors and any separate oil-cooler fans.
- Second compressor, booster, nitrogen generator or blower.
- Lighting, welding sets, pumps, site offices and air conditioning.
Then plan the starting sequence. Start the largest motor first, while the generator carries least load. Never let two large motors start together; compressor controllers can usually be set with a start delay after power returns.
Hyderabad conditions: heat and derating
Generators are rated at standard ambient conditions. In April and May, sites in Telangana and Andhra Pradesh regularly see ambient temperatures above 40 °C, and inside a poorly ventilated enclosure it is hotter still. Engine output falls with heat, and alternator windings run hotter. Keep the generator in open shade with its radiator air flowing freely, keep the compressor’s cooling air separate from the generator’s hot exhaust air, and when in doubt choose the next size up.
Electrical checks before connecting
- Voltage, phase and frequency match: 415 V, three-phase, 50 Hz for most industrial compressors.
- Correct phase rotation: a screw compressor running backwards can be damaged within seconds.
- Cable size suited to the current and the run length, with proper glands and earthing.
- Circuit breaker and overload settings that allow the starting surge without nuisance tripping.
- Earthing and neutral arrangement agreed with the electrician, especially where the set feeds other equipment.
Combined hire: compressor and generator together
Reddy Compressors and Reddy Generators are run by the same management, with more than two decades of field experience. When a site needs both machines, we select them together, check the starting method and the full site load, and deliver a matched pair: the compressor’s starting demand, the generator’s response and the cabling are all considered before anything reaches site. For sites where no electricity is planned at all, a diesel portable compressor may be the simpler answer, and we will advise on that too.
Worked example: one compressor and the rest of the site
A building site runs a 37 kW star-delta screw compressor, its 1.5 kW refrigerated dryer and about 10 kW of lighting, pumps and small tools, all from one generator.
- Compressor running load: 37 ÷ (0.92 × 0.85) = 47.3 kVA.
- Other loads: 11.5 kW ÷ (0.92 × 0.85) = 14.7 kVA.
- Starting requirement: 2 × 37 + 14.7 = 88.7 kVA, with the other loads already running when the compressor starts.
- Running requirement: (47.3 + 14.7) ÷ 0.8 = 77.5 kVA.
The starting figure decides: a 100 kVA generator, the next common size above 88.7 kVA. If the site can start the compressor first and switch on the lighting and pumps after it reaches full speed, the starting requirement falls to 74.0 kVA, and an 82.5 kVA set would do, because the running load of 62.0 kVA is 75% of its rating, inside the 80% limit. That one change in the start-up order saves a size of generator for the whole job.
Common mistakes we see on site
- Sizing on running kW alone. A 37 kW compressor on a 62.5 kVA generator runs happily once started, but direct-on-line it will not start at all.
- Starting everything together. When grid power fails and the generator takes over, every motor on the site tries to restart at once. Stagger the restarts with timers or controller settings.
- Long, thin cables. Voltage drop in the cable adds to the generator’s dip during starting. Size the cable for the starting current as well as the running current.
- Ignoring phase rotation after a changeover. Check rotation every time the supply is reconnected; a screw compressor running backwards can be damaged within seconds.
- Running a large set nearly empty. A generator idling at 10–20% load for weeks builds carbon and unburnt fuel in the exhaust. Match the set to the real load, or add a second smaller set for night and weekend running.
How Reddy Compressors helps
Reddy Compressors and Reddy Generators work under the same management, with more than two decades of field experience. When a site needs both machines, we check the compressor’s starting method, the full site load and the cabling together, and supply a matched pair for hire or purchase. Where no electricity is planned at all, we will also tell you when a diesel portable compressor is the simpler answer. Our service engineers can also check an existing compressor-and-generator pair that trips or fails to start, and recommend the change, whether that is the starting method, the cable, the restart timing or the generator itself.
What to send us
- Compressor motor rating in kW and its starting method: direct-on-line, star-delta, soft starter or VSD
- Every other load that will run at the same time, with its kW
- Supply needed: voltage, phase and frequency
- Cable route length from generator to compressor
- Site conditions: hottest month, enclosure or open shade
- Whether the compressor will later move to grid power
Call or WhatsApp +91 99590 60718 or +91 92468 88812, or email info@reddycompressors.com or reddycompressors@gmail.com. We are open 7 days a week, 8:30 am to 8:30 pm.
Frequently asked questions
What size generator do I need for an air compressor?
Size it for starting. As a planning guide allow about 3 × the motor kW in generator kVA for direct-on-line starting, 2 × for star-delta, 1.75 × for a soft starter and 1.5 × for a VSD, add the other loads, and make sure the total running load stays below 80% of the generator rating. A 37 kW star-delta compressor needs about 74 kVA, so an 82.5 kVA generator.
Why does my compressor not start on the generator?
Usually the generator cannot supply the motor’s starting surge, so the voltage collapses and the starter drops out. Other causes are another large load starting at the same moment, wrong phase rotation, undersized cables, or a governor that cannot hold frequency. Check the starting method and the generator size first.
Is a VSD compressor better on a generator?
A VSD compressor draws the least starting current, about 1–1.5 × full-load current, so it starts easily on a smaller set. Its drive creates harmonics, so allow about 1.5 × the motor kW in generator kVA, choose a set with good voltage regulation, and follow the compressor maker’s generator requirements.
Can I use the same generator for the compressor and the dryer?
Yes, if the generator is sized for both. Add the dryer’s power to the other running loads, size the generator for the total, and start the compressor first, while the generator is least loaded. Many compressor controllers can delay their start after power returns, so the compressor and dryer do not start at the same moment.
Does hot weather affect the generator size?
Yes. Generator output is rated at standard conditions, and in Hyderabad summers above 40 °C both the engine and the alternator lose capacity. Keep the set in open shade with free air flow, and choose the next size up when the site is hot or the enclosure is cramped.
Can you supply a compressor and a generator together?
Yes. Reddy Compressors and Reddy Generators are under the same management, so we can select, match and deliver both machines together, for hire or purchase, with the starting method, cabling and full site load checked in advance. Call or WhatsApp +91 99590 60718 with the compressor details and the other site loads.
Is a diesel portable compressor better than an electric compressor on a generator?
On a site with no planned electricity and no other electrical loads, a diesel portable compressor is often simpler: one machine, no cabling and no starting issues. Where the site already needs a generator, or the compressor will later move to grid power, an electric compressor on a matched generator makes sense.
Should the generator be sized for a future second compressor?
If a second compressor is planned within a year or two, size the generator for both, with the larger motor starting first and the second starting only after the first has reached full speed. If the second machine is uncertain, size for today’s load and plan a second generator later, so the first set does not run nearly empty for years.
Related pages
- Electrical supply for rental compressors
- Diesel or electric temporary air
- Starters and electrical protection
- Why compressor motors trip
- VSD reliability and drive systems
- Generator size calculator (Reddy Generators)
- Screw compressor service in Hyderabad
- Screw compressor price in India: how to compare quotes
Technical content reviewed by D. Srinivas Reddy, Managing Partner and service engineer, Reddy Compressors. Last updated 22 November 2026. How our engineering content is reviewed.