Foundry compressed airsystem integration
Compressed-Air Architecture for Moulding, Core-Making, Shakeout, Fettling, Cleaning, Pneumatic Handling, Instrumentation and Hostile Foundry Environments
Controlled page intent — Assess moulding, cleaning, instrumentation and hostile ambient conditions as one plant-wide compressed-air integration problem. |
Control item | |
|---|---|
Parent page | |
Proposed route | /industries/foundry-compressed-air-system-integration/ |
Required asset | Foundry Duty Segregation Matrix |
Primary decision | How should a foundry segregate and supply moulding, cleaning, instrument/control and auxiliary air so dusty, hot and cyclic production conditions do not destabilise critical users? |
Completion standard | Unique engineering body + segregation matrix + calculations + decision guidance + troubleshooting + FAQs + SEO/AEO/AI-search/GEO package |
Worked figures are illustrative engineering examples unless identified as measured project data.
1. Engineering Answer — A Foundry Is Several Compressed-Air Systems Sharing One Utility
A foundry should not be engineered as one undifferentiated compressed-air load. Moulding lines, core-making machines, shakeout and fettling areas, shot or abrasive cleaning support, pneumatic conveying, actuators, process valves, maintenance tools and instrument/control users behave very differently. Some loads are cyclic and violent, some are sustained, some can tolerate short pressure dips, and some should remain stable even while a large cleaning or blow-off demand starts nearby.
The plant therefore needs a pressure-and-quality architecture, not simply a larger compressor. The strongest design begins by mapping each user to its required pressure, flow pattern, duty cycle, air-quality sensitivity, production consequence and environmental exposure. These users are then grouped into zones that can share supply without one category degrading another. High-demand cleaning should not be allowed to dictate plant-wide pressure, and sensitive control air should not be left vulnerable to the same restrictions, condensate paths and pressure swings as general foundry service air.
Foundry conditions intensify the problem. Airborne dust, sand, metallic fines, radiant heat, high ambient temperatures, water from washdown or cooling activities, vibration and difficult maintenance access can degrade compressor intake conditions, filters, drains, valves, hoses and instruments. A system that is adequate in a clean workshop can become unstable in a foundry if these environmental loads are ignored.
Core principle — Segregate by duty and consequence. Size the source from representative coincident demand, then engineer distribution so the most sensitive user receives the required pressure and quality during the most demanding credible production state. |
2. Scope and Engineering Boundaries
It links production duties to source capacity, distribution, storage, treatment, controls, environmental protection, continuity and measurement. It does not replace machine-builder specifications, furnace/burner design, dust-extraction engineering, combustion-air systems, process-gas systems, casting metallurgy controls or specialist hazardous-process assessments.
Separate specialist / machine responsibility | |
Foundry compressed-air user mapping and segregation | Machine OEM pressure, quality and cycle requirements |
Coincident demand and transient assessment | Furnace, burner and combustion-air design |
General, cleaning and instrument/control air zoning | Dust extraction and ventilation system design |
Distribution pressure budget and restrictions | Casting process recipe and metallurgical parameters |
Storage and recovery for cyclic loads | Specialist process gases and oxygen/fuel systems |
Compressor-room environmental integration | Electrical, fire and plant civil design |
Continuity, monitoring and change control | Machine safety circuits and functional-safety validation |
3. Required Asset — Foundry Duty Segregation Matrix
It prevents the common mistake of assuming that all pneumatic users belong on one pressure header with one treatment level. Each user or user group should be assigned a pressure band, flow profile, air-quality sensitivity, production criticality, environmental exposure and preferred supply zone.
Foundry area / user | Demand behaviour | Quality / stability need | Recommended zone | Primary integration risk |
|---|---|---|---|---|
Moulding line actuators and clamps | High-cycle intermittent | Stable pressure; normal machine-quality air | Production service air | Simultaneous cycles cause local dips |
Core-making machines | Cyclic + purge/blow functions | Machine-specific dryness/cleanliness | Production service / treated branch | Moisture or contamination affects repeatability |
Sand gates, slides, valves | Intermittent | Moderate | General production air | Dust ingress at actuators and solenoids |
Pneumatic conveying / sand transfer interfaces | Sustained or batch high flow | Process-specific | Dedicated process branch where justified | High flow destabilises shared header |
Shakeout / fettling tools | Intermittent high flow | Moderate | Heavy service air | Tool peaks and long hoses |
Cleaning / blow-off | Potentially sustained and discretionary | Moderate | Controlled cleaning branch | Artificial demand dominates station load |
Shot-blast / blast support | High sustained flow where pneumatic | Process-specific | Dedicated high-flow branch/source | Shared-header pressure collapse |
Instrument and control air | Low flow, high consequence | High stability and cleanliness | Protected instrument/control branch | Plant transients trip valves or instruments |
Maintenance tools | Variable, non-production | Moderate | Maintenance/service branch | Uncontrolled use during production peaks |
Quality / test stations | Usually low flow | High stability / cleanliness | Protected treated branch | Production activity disturbs test result |
The matrix should be revision-controlled when moulding cells, core machines, sand systems, cleaning methods or production rates change. A new user should not be connected to the nearest convenient header before its pressure, quality and simultaneity effects are understood.
4. Map the Foundry Process Before Selecting Capacity
Foundry compressed-air demand follows the production route. The useful engineering map links compressed-air events to metal preparation, mould preparation, core production, pouring support, cooling, shakeout, fettling, cleaning, finishing, inspection and dispatch. The compressor system must follow the actual sequence of plant activity rather than a simple list of connected machines.
Production stage | Typical compressed-air role | Demand characteristic | Engineering note |
|---|---|---|---|
Mould preparation | Actuation, clamping, gates, cleaning | High-cycle intermittent | Check line cycle coincidence |
Core making | Actuation, blowing/purge, handling | Cyclic with short peaks | Verify OEM flow basis and moisture sensitivity |
Pouring support | Valves, actuators, controls | Low to moderate, high consequence | Protect against pressure disturbances |
Cooling / transfer | Conveyors, gates, actuators | Intermittent | Dust protection important |
Shakeout | Tools, cylinders, auxiliary equipment | Bursty / heavy duty | Local restriction often dominates |
Fettling / finishing | Grinding/chipping tools, cleaning | Intermittent to sustained | Tool hose and coupling loss critical |
Surface cleaning | Blow-off / blasting support | Sustained high flow possible | Separate uncontrolled cleaning load |
Inspection / test | Fixtures, gauges, controls | Low flow, sensitive | Use protected branch where required |
5. Demand Engineering — Connected Flow Is Not Plant Demand
Summing every pneumatic nameplate typically overstates normal demand, while ignoring simultaneous cycle peaks can understate the short-duration duty that causes pressure problems. Foundry demand should therefore be modelled by operating state: normal production, changeover, maintenance, peak cleaning, restart, reduced-shift operation and credible concurrent events.
For each group, define: number installed, number expected to operate simultaneously, flow per active user at stated reference conditions, duty factor within the assessment interval, and whether the load is sustained or transient. Separate uncertainty from deliberate design margin rather than hiding both inside one oversized allowance.
Coincident demand method — Q_design = Σ (N_active × q_user × duty factor) + verified sustained process loads + justified uncertainty allowance. Short transient events should also be checked against local storage and dynamic pressure response. |
Input | Illustrative value | Purpose |
|---|---|---|
Moulding cells active | 8 cells × 0.45 m³/min × 0.65 | Average coincident moulding duty |
Core machines active | 3 × 0.60 m³/min × 0.70 | Core-making contribution |
Fettling tools | 6 × 0.35 m³/min × 0.50 | Intermittent hand-tool load |
Cleaning branch | 2.2 m³/min sustained during scheduled cleaning | High-flow discretionary load |
Instrument/control branch | 0.55 m³/min | Protected base load |
Leak / uncertainty allowance | Measured or justified separately | Avoid hidden double-counting |
Using the illustrative duty factors above gives approximately 2.34 + 1.26 + 1.05 + 2.20 + 0.55 = 7.40 m³/min before any measured leakage or explicit uncertainty allowance. If cleaning can be scheduled outside production peaks, the normal production design state can be materially different from the cleaning state. That scheduling decision may be more valuable than simply raising compressor discharge pressure.
6. Moulding and Core-Making Air Integration
Moulding and core-making equipment often combines repetitive actuator cycles with short blow, purge or ejection events. The average flow may appear modest, but the instantaneous demand during a coordinated line cycle can be much higher. If several machines share one undersized cell branch, pressure at the machine can fall even when the compressor room remains within its setpoint band.
Machine-side question | Why it matters |
|---|---|
What pressure is required at the machine inlet while cycling? | Separates useful machine pressure from compressor discharge pressure |
Which events occur simultaneously across the line? | Defines transient coincidence |
Does the machine include internal receiver volume? | Changes local transient behaviour |
Are quick couplings or small regulators fitted? | Potential dominant restriction |
Is any function moisture or contamination sensitive? | Defines final treatment boundary |
What happens on low pressure? | Determines production criticality and recovery priority |
Where practical, use a cell manifold sized for combined branch flow, keep the final connection to each machine short, and place pressure measurement points at the cell header and critical machine inlet. A single gauge at the compressor discharge cannot reveal a machine-side transient.
7. Cleaning, Blow-Off and Artificial Demand
Cleaning is one of the most important foundry loads to govern because open blow-off can consume large volumes continuously, especially where dust and sand make housekeeping frequent. Uncontrolled blow-off may become the reason the entire plant is operated at unnecessarily high pressure. The correct response is to define the cleaning objective, nozzle or tool, duty duration and acceptable pressure, then choose an efficient method and dedicated branch where useful.
Cleaning use | Control approach |
|---|---|
Machine cavity / fixture cleaning | Use engineered nozzles and local isolation; avoid permanently open jets |
Floor / general housekeeping | Prefer suitable industrial cleaning methods; do not normalise unrestricted air use |
Part cleaning | Confirm surface-quality need and minimum effective pressure |
Dust removal from control cabinets | Do not use uncontrolled compressed air where it can drive dust into sensitive equipment |
Maintenance blow-down | Schedule outside production peaks when practical |
A plant that reduces an unnecessary 1.0 m³/min cleaning load can often achieve more useful capacity than a plant that installs a larger compressor while leaving the waste unchanged.
8. Instrument and Control Air Must Be Protected
Foundries may use pneumatic actuators, process valves, dampers, positioners, instrumentation and control devices whose individual flow is small but whose failure consequence is high. These users should not be exposed to the same uncontrolled pressure excursions and contamination risks as heavy service-air consumers.
Protection layer | Engineering intent |
|---|---|
Dedicated take-off from stable header | Avoids connection downstream of heavy intermittent restriction |
Appropriate final filtration/drying | Protects valves, instruments and small orifices |
Local regulator / protected pressure band | Prevents high general-service pressure from being necessary |
Small local receiver where justified | Supports short disturbance ride-through, not sustained undersupply |
Pressure alarm / trend point | Makes degradation visible before a trip |
Check/isolation arrangement where justified | Controls reverse flow and maintenance impact |
The strongest architecture is often a shared generation plant feeding separate distribution zones: heavy service, production machines, cleaning/high-flow users and protected instrument/control air. Separation does not necessarily mean separate compressors for every duty; it means intentional pressure, quality and contingency boundaries.
9. Pressure Architecture and Dynamic Pressure Budget
The machine requirement is the starting point. Required compressor-room pressure equals the critical point-of-use requirement plus the credible losses through treatment, main distribution, branches, valves, regulators, filters, hoses and transient allowances. Every unnecessary restriction increases the pressure that the source must maintain.
Pressure-budget element | Illustrative loss at design flow |
|---|---|
Treatment train | 0.18 bar |
Main ring / trunk | 0.22 bar |
Area branch | 0.16 bar |
Machine regulator / filter | 0.20 bar |
Hose / coupling / local fittings | 0.14 bar |
Dynamic allowance | 0.20 bar |
Total distribution allowance | 1.10 bar |
If a critical moulding machine requires 6.2 bar(g) at its inlet under load, an illustrative source target based on the above budget would be about 7.3 bar(g). The engineering objective is not to accept that target permanently; it is to test each loss and reduce avoidable restrictions. If local connection losses can be cut by 0.25 bar, the source setpoint may also be reducible after field verification.
Diagnostic rule — Log pressure simultaneously at compressor header, area header and critical machine inlet during the same production event. A static no-load pressure reading is not a valid pressure-budget test. |
10. Distribution Architecture for Dusty Production Areas
A foundry distribution system should minimise dead legs, water traps, poorly supported drops and exposed flexible hose. Permanent high-flow routes should use appropriately sized hard piping with maintainable isolation. Local manifolds should be positioned so final hoses remain short and protected from traffic, hot surfaces, sharp edges and moving equipment.
Distribution feature | Preferred engineering intent |
|---|---|
Main ring / loop where practical | Multiple flow paths and lower pressure drop |
Zoned isolation | Maintenance without unnecessary plant shutdown |
Top or controlled take-offs where appropriate | Reduce condensate carryover into drops |
Drains at managed low points | Prevent water accumulation |
Full-bore valves and fittings | Avoid hidden restrictions |
Machine manifold near user cluster | Short final connections and easier measurement |
Protected hose routing | Reduce abrasion, heat and vehicle damage |
Tagged branches | Supports troubleshooting and change control |
11. Hostile Ambient Conditions — Dust, Heat, Water and Vibration
Foundry environments can be hostile to both compression equipment and distribution components. The compressor room should be treated as a protected utility space with controlled intake and cooling conditions, not as another dusty production bay. Dust loading can increase intake restriction and cooler fouling; high ambient temperature reduces cooling margin; radiant heat can distort apparent ambient conditions; poor ventilation recirculates hot discharge air; washdown or rain ingress can damage electrical and control systems.
Environmental exposure | Failure mechanism | Control direction |
|---|---|---|
Sand / silica / metallic dust | Intake/filter loading, cooler fouling, valve contamination | Cleaner intake location, filtration, housekeeping and condition monitoring |
High ambient / radiant heat | Reduced cooling margin, elevated discharge temperature | Ventilation assessment, hot-air rejection, intake separation |
Water / washdown | Corrosion, electrical risk, drain overload | Equipment location, ingress protection and drainage |
Vibration / impact | Loose fittings, sensor issues, hose wear | Mounting, support and inspection |
Hot surfaces / sparks near hoses | Hose damage and leakage | Route segregation and protection |
Restricted maintenance access | Delayed cleaning and servicing | Maintain service clearances and lifting access |
12. Compressor-Room and Environment Interface
The compressor room must reject both the compressor heat load and the environmental contamination arriving from the plant. Intake air should be drawn from the cleanest practical location consistent with equipment requirements, while hot discharge air should be exhausted so it cannot recirculate to the intake. Service access, cooler cleaning, drain maintenance and filter replacement should remain practical even during production.
Room interface check | Question to resolve |
|---|---|
Intake source | Is intake air cleaner and cooler than the surrounding foundry floor? |
Cooling-air path | Can hot exhaust recirculate into compressor intake? |
Dust ingress | How will doors, louvers and service openings affect contamination? |
Heat rejection | Is ventilation capacity adequate for the full operating state? |
Drainage | Can condensate systems operate without flooding or contamination spread? |
Maintenance access | Can coolers, filters, motors and major assemblies be serviced safely? |
Expansion | Is there physical and electrical capacity for future plant load? |
13. Air-Quality Boundaries
Foundry compressed air should be specified by user need, not by one blanket quality level. General pneumatic cylinders may tolerate a different quality envelope from instruments, inspection equipment, finish-sensitive applications or any air that can influence a downstream product surface. Over-treating the entire plant wastes pressure and energy; under-treating a sensitive branch creates reliability and quality risk.
Zone | Typical users | Quality strategy |
|---|---|---|
General heavy service | Maintenance tools, robust actuators | Plant treatment suited to equipment and environment |
Production machine air | Moulding/core machinery | Stable dry/clean air per machine requirements |
Instrument/control | Valves, positioners, small orifices | Protected final treatment and monitoring |
Finish/inspection-sensitive | Test or surface-sensitive functions | Dedicated final treatment if process requires |
Special process air | Any direct process-specific use | Define separately from generic plant air |
14. Condensate, Drains and Moisture Control
Hot compressed air leaving the compressor carries water vapour. As air cools in long plant mains and cooler production areas, condensate can form if the treatment and drainage strategy is inadequate. Foundries often combine hot production zones with cooler peripheral pipe runs, making drainage location and treatment performance important.
Use correctly selected separation and drying for the actual pressure, flow and ambient conditions.
Keep automatic drains maintainable and visible; a blocked drain can become a system-wide contamination source.
Avoid low-point traps created by temporary hoses or sagging pipe.
Do not infer dryness from absence of visible water at one outlet; verify the critical branch condition when required.
After major distribution changes, re-check condensate behaviour because flow direction and cooling patterns may change.
15. Local Storage and Transient Management
Local receivers can help when a moulding or core-making event has a short flow peak that would otherwise pull down the local header. Storage should be placed after confirming that the problem is transient. A receiver cannot compensate for a sustained undersized compressor, an undersized main or a continuously open cleaning load.
Transient-storage concept — Available storage depends on receiver volume, absolute pressure swing and the duration of the event. The pressure band must remain above the minimum acceptable machine inlet pressure after all downstream restrictions are included. |
Use case | Storage can help? | Condition |
|---|---|---|
Short machine clamp / eject peak | Yes | Source can recover between cycles |
Several seconds of purge demand | Often | Verify allowable local pressure decay |
Continuous pneumatic conveying shortfall | No | Requires sustained capacity/distribution correction |
Open cleaning nozzle left on | No | Eliminate or control demand |
Protected instrument ride-through | Potentially | Only with defined isolation and recovery strategy |
16. Source Architecture and Compressor Sequencing
In multi-compressor stations, the goal is to keep the minimum number of machines operating efficiently while preserving the required reserve philosophy. A variable-speed trim machine can be useful when demand varies materially, but it should operate inside an efficient range rather than masking poor base/trim selection.
Demand pattern | Architecture consideration |
|---|---|
Stable high base load | Efficient base machine(s) with planned reserve |
Wide shift-to-shift variation | Base + trim strategy; verify turndown and control interaction |
Frequent cleaning peaks | Demand control or dedicated branch before adding base capacity |
Critical 24/7 controls | Reserve and protected branch; avoid common-cause restrictions |
Expansion in phases | Modular capacity and distribution provisions |
17. Redundancy and Production Continuity
Foundry continuity should be based on production consequence, not a generic “N+1” label applied without context. Identify the minimum air requirement needed to keep critical controls safe, protect in-process work, complete a controlled stop or maintain selected production cells. Then test whether the remaining source, treatment and distribution paths can actually deliver that requirement.
Continuity class | Example users | Required response |
|---|---|---|
A — protected | Instrument/control, critical valves, selected safety-related pneumatic functions | Fast recovery / protected path as defined by plant risk review |
B — production critical | Moulding/core cells that create major production loss | Restore in planned priority |
C — schedulable high-flow | Cleaning, some maintenance, noncritical blasting support | Shed during constrained operation |
D — discretionary | General blow-off / housekeeping | Stop first during capacity event |
Continuity analysis should include compressor failure, dryer/filter restriction, main-header isolation, power loss, control failure and a major downstream rupture. Reserve capacity that cannot reach the user because of a closed isolation valve or failed treatment train is not useful redundancy.
18. Controlled Restart After Air-System Interruption
A full foundry restart can create a demand spike as multiple machines refill, valves cycle and operators begin cleaning simultaneously. Staged restart protects pressure stability and reduces the risk of repeated trips.
Restore the protected instrument/control branch and verify stable pressure.
Bring critical production zones online in the agreed sequence.
Allow local receivers and machine circuits to repressurise.
Restart high-cycle moulding/core machines in groups rather than simultaneously.
Keep cleaning and discretionary service loads isolated until the production header is stable.
Confirm pressure at critical endpoints before releasing the full plant.
19. Measurement Architecture
A foundry air system should be measurable at the points where engineering decisions are made. One compressor-room pressure transmitter is insufficient for diagnosing local plant instability.
Measurement point | Decision enabled |
|---|---|
Compressor discharge header | Source pressure and sequencing |
Post-treatment header | Treatment loss |
Main ring / far end | Distribution loss and ring balance |
Moulding zone header | Production-zone stability |
Cleaning / high-flow branch | Demand magnitude and controllability |
Instrument/control branch | Protected pressure and quality |
Critical machine inlet | Actual machine condition |
Flow meter on major zones where justified | Demand profile, leakage and expansion decisions |
20. Energy and Capacity Optimisation
The largest foundry opportunity is often to reduce the pressure and flow that do not create production value. Pressure should be set by the most demanding justified user after avoidable restrictions are removed. High-pressure islands should be solved locally where practical rather than forcing the entire plant to the highest machine requirement.
Optimisation lever | Engineering effect |
|---|---|
Repair leaks and open drains | Recovers real capacity |
Control cleaning / blow-off | Reduces sustained artificial demand |
Reduce local restrictions | Allows lower header pressure |
Zone high-pressure users | Prevents plant-wide overpressure |
Sequence compressors properly | Reduces unloaded / inefficient operation |
Maintain filters and coolers | Protects pressure and temperature performance |
Measure before expansion | Avoids buying capacity to compensate for system losses |
21. Reliability and Maintenance Strategy
Maintenance must account for foundry contamination. Filter differential pressure, cooler cleanliness, drain operation, compressor intake condition, hose damage, regulator condition and solenoid contamination should be reviewed more aggressively where dust and heat loading are severe.
Asset | Foundry-specific reliability focus |
|---|---|
Compressor intake filter | Dust loading trend and clean intake condition |
Coolers | Fouling, recirculation and thermal margin |
Dryers / filters | Pressure drop and actual treated-air performance |
Automatic drains | Blockage and condensate removal |
Main isolation valves | Operability and tagging |
Hoses / couplings | Abrasion, heat damage and flow restriction |
Machine FRL / regulators | Restriction, setting drift and contamination |
Pressure / flow sensors | Accuracy and useful placement |
22. Typical Foundry Failure Modes
Symptom | Likely causes | First checks |
|---|---|---|
Moulding machines slow during shift peak | Local branch restriction, simultaneous cycles, low source reserve | Trend source, zone and machine inlet pressures together |
Plant pressure high but machine pressure low | Regulator/filter/coupling/hose restriction | Measure pressure before and after local components |
Control valves unstable during cleaning | No segregation; cleaning load depresses shared header | Log protected branch during cleaning event |
Water at remote machines | Treatment/drain issue or cooling in distribution | Check dryer, separators, drains and low points |
Compressor high-temperature trips | Dusty cooler, poor ventilation, hot-air recirculation | Inspect intake/cooling path and room temperature |
Frequent filter blockage | High dust ingress or wrong location | Review room/inlet contamination control |
Capacity shortage only after expansion | New loads added without updated simultaneity model | Rebuild zone demand profile |
High energy with normal production | Leaks, high pressure, unload time, cleaning waste | Audit pressure, flow and compressor state |
23. Worked Scenario — Moulding Expansion Without Plant-Wide Pressure Increase
Assume an existing foundry operates at 7.4 bar(g) compressor-header pressure. A new moulding cell requires 6.1 bar(g) minimum at its machine inlet. During peak production the existing system loses 0.95 bar from source to the new cell, giving an estimated 6.45 bar(g) at the machine. The project team initially proposes raising the compressor setpoint by 0.5 bar.
Instead, the engineer measures the loss components and finds 0.28 bar across an undersized area branch, 0.22 bar across a heavily loaded filter/regulator assembly, 0.15 bar in hose/couplings and 0.30 bar across the remaining main/treatment path. By replacing the area branch and correcting the local filter/regulator arrangement, 0.32 bar of avoidable loss is removed. The machine can then operate with improved margin without increasing the entire plant pressure.
Decision lesson — The correct question is not “How much should the compressor pressure be increased?” It is “Where is the pressure being lost during the actual machine event, and can that loss be removed locally?” |
24. Expansion and Change Control
Foundries evolve continuously: new moulding cells, automation, core machines, cleaning systems, sand handling, inspection stations and shift patterns are added. Each material change should trigger a demand and pressure review before connection.
Change trigger | Required review |
|---|---|
New moulding/core cell | Demand, cycle coincidence, local branch and pressure budget |
New cleaning method | Sustained flow and scheduling |
Added pneumatic conveying | Dedicated process duty and source impact |
New instrument/control users | Protected branch capacity and treatment |
Higher production rate | Simultaneity and recovery time |
Compressor replacement | Delivered capacity at actual pressure and control compatibility |
Distribution reroute | Pressure loss, drainage and isolation |
New hot/dusty production zone | Compressor-room and environmental exposure review |
25. Commissioning and Acceptance Sequence
Confirm the Foundry Duty Segregation Matrix against actual machine connections.
Verify source capacity and compressor control logic under representative demand.
Confirm treatment train pressure loss and drain operation.
Pressure-test and inspect distribution, isolation, manifolds and temporary connections as applicable.
Log source, zone and critical endpoint pressure during representative moulding/core cycles.
Run the defined high-flow cleaning state and confirm it does not destabilise protected users.
Verify instrument/control branch pressure and quality boundaries.
Test standby or alternate supply arrangements defined by the continuity plan.
Record baseline flow, pressure and compressor operating state for future comparison.
Issue as-left drawings, valve identification, settings and measurement records.