Why most before-and-after claims fail
A plant replaces a compressor, fixes leaks or fits a variable-speed drive, and next month’s electricity bill is lower. It is tempting to call the difference a saving. Yet the bill may have fallen because a production line was down, because the monsoon cooled the compressor house, because a second shift was cut, or because the meter covers loads other than the compressors. Equally, a real improvement can be hidden by higher output in the “after” period.
A sound comparison separates the effect of the change from everything else that moved at the same time. The method below is the one we use when a customer asks us to show whether a piece of work actually helped. It applies equally to energy, pressure stability, dew point and running hours.
Start by writing the claim you want to test
Before any logger is installed, write the claim as a testable sentence, because each claim needs a different measurement plan.
- “Compressor-station electrical energy per tonne of output fell after leak repair” needs station kWh and production data in both periods.
- “Pressure at the paint shop stayed above 6 bar (87 psig) at peak demand after the header change” needs simultaneous pressure logging at the station and at the critical user.
- “Pressure dew point at the dryer outlet stayed at or below about +3 °C during the summer peak” needs a dew-point sensor at a defined sampling point and ambient temperature records.
- “Unloaded running hours fell after the sequencing change” needs controller hour counters or a power logger on each machine.
Draw the boundary before you measure
Sketch the air path and the electrical supply. Mark every compressor, dryer, filter, receiver, header and branch, the critical users and any parallel air source such as a rented portable. Then mark what the claim is about: one machine, the station, a branch or a process. A reading taken on a single compressor package cannot establish whole-station performance, and a station meter that also feeds cooling-tower pumps cannot isolate compressor energy.
| Claim level | Boundary | Minimum measurements |
|---|---|---|
| Machine | One compressor package | Input power, delivered flow or loaded/unloaded time, discharge pressure |
| Station | All compressors, dryers and auxiliaries | Total station kWh, total delivered flow, header pressure |
| Distribution | Station outlet to critical users | Simultaneous pressure at both ends, flow in the branch |
| Process | A line or user group | Flow to the process, pressure at the point of use, production count |
Choosing a representative baseline
The baseline should represent normal operation, not the worst week. It should be long enough to include the usual shift pattern, weekends and typical production variation; for most plants that means at least one to two full working weeks of logged data. Record the dates, shifts worked, output, ambient conditions, control settings, maintenance state and any unusual events such as a breakdown or a rented standby machine.
Keep the raw baseline data unchanged. If adjustments are later agreed, they are applied to a copy, so anyone reviewing the result can see what was measured and what was calculated.
Matching the after period
The after period should match the baseline as closely as possible: same instruments in the same positions, similar length, similar shift pattern and similar season. Allow time for the change to settle. After a sequencing change, operators often adjust set points for a few days; after leak repair, new leaks start to appear within weeks. State when the after period started and why.
- Confirm instruments are in the same positions and still within their verification status.
- Record the date and description of the change exactly as made, including any set point adjustments.
- Allow a stabilisation period and exclude it from the comparison, stating its length.
- Log for a period comparable to the baseline in length and operating pattern.
- Note every event that could affect demand: new machines, line stoppages, holidays, power cuts.
Normalising for production, weather and pressure
Normalisation means adjusting for documented differences between the two periods, not for convenient ones. The usual factors are:
- Production. Compare energy per unit of output, or energy per delivered m³, where output differs between periods.
- Operating hours. A plant that ran fewer hours will use less air regardless of any improvement.
- Ambient temperature. Hyderabad summers of 40–45 °C raise inlet temperature, reduce dryer capacity and increase cooling load; comparing a May baseline with a December after period is not fair.
- Pressure. Generation pressure has a direct effect on power, typically about 7% more power for each extra bar on an oil-injected screw. If set pressure changed, say so and treat it as part of the intervention or adjust for it openly.
Every adjustment should be written down with its basis. A reviewer should be able to reproduce the adjusted figure from the raw data and the stated method.
Specific power: the most useful single comparison
For energy claims, the most robust single figure is specific power: electrical input divided by delivered free air, usually expressed in kW per m³/min (or kW per 100 cfm). It automatically accounts for changes in demand, provided both power and flow are measured at the same boundary. It still depends on pressure, so compare specific power at the same or corrected generation pressure.
A worked illustration: suppose a station averaged 110 kW while delivering 18 m³/min in the baseline (about 6.1 kW per m³/min) and 96 kW while delivering 17 m³/min after the change (about 5.65 kW per m³/min). The energy fell partly because demand fell, and partly because the station became more efficient. Specific power isolates the second effect. Whether the difference is real depends on the measurement uncertainty, which must be stated alongside it.
Uncertainty and rival explanations
Every measured difference has an uncertainty, made up of instrument accuracy, installation effects, sampling interval and the natural variation in demand. If a claimed improvement is smaller than the combined uncertainty, the honest conclusion is “no measurable change”, not “a small saving”. Where the result matters commercially, it is worth investing in tighter instruments or a longer logging period before the decision rather than after it.
Then list rival explanations and test each one: a production drop, a closed branch, a new leak, a rented machine taken off line, a dryer bypassed, a controller reset. A comparison that cannot rule out obvious rivals should be reported with that limitation in plain words.
Reporting the result honestly
A good comparison report states the claim, the boundary, the baseline and after periods, the instruments, every adjustment and its basis, the result with its uncertainty, and the rival explanations considered. It also says plainly what the result does not show, for example that a station-level saving says nothing about air quality at the users.
Worked example (illustrative): from measurements to rupees and carbon
This example shows how a finished comparison reads when every step is written down. The figures are illustrative, not a named customer.
A packaging plant runs about 6,000 hours a year. Before the work, the logged average demand was 12.0 m³/min (424 cfm) at a specific power of 7.4 kW per m³/min, because two fixed-speed compressors were fighting each other with overlapping pressure bands. Leaks of about 1.5 m³/min were tagged and repaired, a choked line filter and an undersized branch were fixed, the compressors were sequenced on one narrow band, and the generation pressure was then lowered.
| Figure | Before | After |
|---|---|---|
| Average demand | 12.0 m³/min (424 cfm) | 10.5 m³/min (371 cfm) |
| Specific power | 7.4 kW per m³/min (444 J/l) | 6.8 kW per m³/min (408 J/l) |
| Energy a year (6,000 h) | 5,32,800 kWh | 4,28,400 kWh |
| Saving | 1,04,400 kWh a year (19.6%) | |
| Money at ₹8 per kWh | ₹8,35,200 a year | |
| Carbon at 0.72 kg CO₂ per kWh | 75.2 tonnes a year |
The working. Before: 12.0 × 7.4 × 6,000 = 5,32,800 kWh. After: 10.5 × 6.8 × 6,000 = 4,28,400 kWh. Saving: 1,04,400 kWh, and 1,04,400 ÷ 5,32,800 = 19.6%. Money: 1,04,400 × ₹8 = ₹8,35,200. Carbon: 1,04,400 × 0.72 = 75,168 kg, about 75.2 tonnes. Specific power converts simply: 1 kW per m³/min = 60 kJ per m³ = 60 J/l, so 7.4 becomes 444 J/l and 6.8 becomes 408 J/l.
Payback. If the leak repairs, filter, pipework and sequencing together cost ₹6,00,000, the simple payback is ₹6,00,000 ÷ ₹8,35,200 a year = 0.72 years, about 8.6 months. State the tariff and the carbon factor in the report, so the figures can be updated when either changes.
Keeping the saving after the report
Savings fade when nobody watches them: leaks return, filter elements choke again and pressure set points creep upwards after a complaint from one machine. End every comparison with a short monitoring plan:
- Who checks the weekend or idle demand each month, and the figure that should trigger a new leak survey.
- Which pressure set points are fixed, and who may change them.
- When the dryer’s dew point and each filter’s pressure drop are recorded.
- When the next measurement period falls, ideally in the opposite season to the first.
A one-page monthly log in the compressor room keeps the result visible to the people who earned it and gives the next comparison a clean starting point.
How Reddy Compressors helps
We carry out before-and-after measurement as part of air audits and improvement work for plants across Telangana and Andhra Pradesh, following the ISO 11011 assessment method. We log pressure at the station and at critical users, delivered flow, power on each compressor and dew point where air quality is part of the claim. We then report the boundary, instruments, conditions, adjustments and remaining uncertainty, so your management can rely on the result.
As an independent multi-brand specialist we work on ELGi, Atlas Copco, Ingersoll Rand, KAESER, Chicago Pneumatic and other makes, and we are not tied to selling any one brand’s replacement machine. If the measured result shows that a change did not help, we say so and look for the reason. Our office is at Tarnaka, Secunderabad; call +91 99590 60718 or +91 92468 88812.
What to send us
- A description of the change you made or plan to make, and the date
- The claim you want to test, in one sentence
- A sketch or list of compressors, dryers, receivers and main branches
- Any existing data: energy bills, controller hour counters, pressure logs, production records
- Shift pattern and any known changes in production between periods
Frequently asked questions
How do I prove a compressed-air energy saving?
Measure electrical power and delivered flow at the same boundary for a representative baseline period, make one defined change, then measure again for a comparable period with the same instruments. Compare specific power in kW per m³/min rather than raw kWh, adjust openly for documented differences in production, hours and pressure, and state the uncertainty. Bills alone rarely prove a saving.
How long should a baseline measurement period be?
Long enough to capture the plant’s normal pattern of shifts, weekends and production swings. For most factories that means at least one to two full working weeks of continuous logging. Seasonal plants or batch processes may need longer, or separate baselines for each operating mode. A single day, or the worst week of the year, gives a misleading baseline.
Why is my electricity bill lower but my compressor no more efficient?
Energy use falls whenever demand falls, for example through lower production, fewer shifts, a stopped line or cooler weather. None of these means the compressor station has become more efficient. Specific power, which divides input power by delivered air, shows whether efficiency itself changed. If specific power is unchanged, the saving came from lower demand, not the intervention.
Can I compare a summer baseline with a winter result?
Only with care. High ambient temperature raises inlet and cooling-air temperature, reduces dryer capacity and changes compressor loading. In Telangana and Andhra Pradesh the difference between May and December conditions is large. Where seasons differ, record ambient temperature in both periods, compare like-for-like operating hours where possible and state the seasonal limitation clearly in the result.
What if the improvement is smaller than the measurement uncertainty?
Then the honest result is that no measurable change was detected within the accuracy of the method. It does not prove the change failed, but it does not prove success either. Options include extending the logging period, using more accurate instruments at a tighter boundary, or accepting the result and recording it as inconclusive rather than claiming a saving.
Does pressure reduction count as part of the saving?
It can, if it was a deliberate part of the intervention and the lower pressure still meets every critical user. Typically about 7% more power is needed for each extra bar on an oil-injected screw, so pressure changes have a large effect. Report the pressure change explicitly and do not attribute its effect to a different part of the work.
Related pages
Calculators and worked examples
These tools give indicative figures for screening, comparison and for preparing an enquiry. They run in your browser and send nothing. No prices or tariffs are assumed: enter your own to see costs. Efficiencies and other figures shown are example values: replace them with your own. Results are not a performance guarantee or a design certificate; final selection is confirmed by a service engineer against the machine data sheet and the site.
Specific power comparison
Compare two compressors on what matters over life: the electrical power needed per unit of air delivered, and what that costs a year.
The worked example below shows the method with fixed numbers. Turn on JavaScript to change the inputs.
Worked example
Inputs
- Machine A: input power (kW): 75
- Machine A: delivered flow (m³/min): 11.5
- Machine B: input power (kW): 80
- Machine B: delivered flow (m³/min): 12.6
- Running hours per year: 6,000
- Air actually needed (m³/min): 11
Result
- Machine A specific power: 6.52 kW per m³/min
- Machine B specific power: 6.35 kW per m³/min
- Energy to deliver the air needed: A: 4,30,435 kWh per year
- Energy to deliver the air needed: B: 4,19,048 kWh per year
- Energy difference: 11,387 kWh per year in favour of B
- Cost difference: Enter your electricity tariff (cost per kWh) above
Method. Specific power = input kW ÷ delivered flow (m³/min) at the same pressure and reference conditions. Annual cost = kW × hours × tariff. Use the full-load input power on the same test basis for both machines.
What to take from it. A small gap in specific power is multiplied by thousands of running hours. Compare on the same pressure and reference conditions.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and service engineer, Reddy Compressors. Last updated 17 October 2026. How our engineering content is reviewed.
Specific power uncertainty budget
Combine the uncertainties of package power and delivered flow into an expanded uncertainty for specific power, find the dominant contributor, and test whether a difference from another option is real.
The worked example below shows the method with fixed numbers. Turn on JavaScript to change the inputs.
Worked example
Inputs
- Measured package power (kW): 90
- Power instrument figure is: Specification limit ± (rectangular, ÷√3)
- Power logger and clamps accuracy (± % of reading): 1.5
- Standard deviation of the repeated power readings (kW): 0.9
- Number of averaged power readings: 36
- Measured delivered flow (m³/min): 14
- Flow meter figure is: Specification limit ± (rectangular, ÷√3)
- Flow meter accuracy (± % of reading): 3
- Flow installation effect, estimated (± % of reading): 2
- Coverage factor k: 2
- Specific power of the option to compare, 0 to skip (kW per m³/min): 0
- Expanded uncertainty of that option, used only if a comparison value is entered (± %): 0
Result
- Specific power: 6.43 kW per m³/min
- Power accuracy (relative standard uncertainty): 0.87%, 15% of the variance
- Power repeatability (relative standard uncertainty): 0.17%, 1% of the variance
- Flow meter accuracy (relative standard uncertainty): 1.73%, 59% of the variance
- Flow installation effect (relative standard uncertainty): 1.15%, 26% of the variance
- Combined relative standard uncertainty: 2.26%
- Expanded uncertainty (k = 2): ± 4.52% = ± 0.29 kW per m³/min
- Result: 6.43 ± 0.29 kW per m³/min (6.14 to 6.72)
- Dominant contributor: Flow meter accuracy
Method. GUM method for y = P ÷ Q (a quotient, so relative uncertainties combine). For the power instrument and the flow meter, choose how the figure is stated: a ± specification limit (rectangular, u = a ÷ √3) or a calibration-certificate expanded uncertainty at k = 2 (normal, u = U ÷ 2). The installation estimate is a ± limit, rectangular. Repeatability (Type A): u = s ÷ √n, relative to P. Combined relative standard uncertainty u_c = √(Σ u_i²); expanded U = k × u_c (k = 2 gives about 95% for a near-normal result with enough readings). Comparison: the difference between the two specific powers is treated as real if it exceeds √(U₁² + U₂²) in absolute terms (independent measurements at the same k). Not covered: wrong boundary or units (errors, not uncertainty) and an unrepresentative test period.
What to take from it. Spend measurement effort on the largest contributor; in compressed-air audits that is usually the flow measurement.