Engineering tools

Part-load fleet dispatch calculator

10 min read10 sections

Jump to the calculator ↓

Why dispatch matters as much as machine efficiency

A compressor room with three or four machines can waste a surprising amount of energy even when every compressor is individually efficient. The loss comes from how the machines are combined. Typical examples are the wrong unit carrying base load, two fixed-speed machines both partly unloaded, a variable-speed drive (VSD) unit forced to run below its stable minimum speed, or a large machine left online simply to provide reserve that could have come from a smaller unit.

Each of these states can deliver exactly the same plant flow while drawing noticeably more kilowatts. Because a compressor room often runs 6,000 hours a year or more, a few kilowatts of avoidable load becomes tens of thousands of kWh. Dispatch is therefore a decision that should be calculated, not left to whichever pressure settings were entered on the day of commissioning.

The calculator answers five practical questions:

  • Which feasible combination of machines should carry a specified demand?
  • Which compressor should act as the trim machine, and is it inside its stable range?
  • How much running and standby reserve remains in that state?
  • What total package power does the chosen state require, and what is the specific power in kW per m³/min?
  • How does the best state change as demand moves across the day, week or year?

What the calculator works out

ModeWhat you enterWhat you get
Single demand pointOne plant demand at one required pressureLowest-kW feasible state plus the next-best alternatives
Demand sweepA range of demands in stepsRecommended combination for each flow band and the switching points (run the live tool once per demand step)
Annual load profileHours spent in each demand bandWeighted annual kWh by dispatch state (run the live tool once per demand band and weight each result by its hours)
Reserve-constrainedA reserve rule such as N+1The best state that also satisfies the reserve rule
Scenario compareTwo fleet or rule definitionsBefore and after kWh for a sequencing change, a new machine or a machine out of service (run the live tool once for each case and compare)

Put every machine on a common basis first

Dispatch comparisons are only valid when every machine is described on the same basis. A common mistake is to mix a nameplate capacity for one machine, a catalogue free air delivery (FAD) for another and a measured figure for a third. Before any combination is ranked, check the following:

  • Delivered flow: convert every capacity point to one reference basis using the FAD and reference condition conversion tool. FAD at the stated inlet conditions is the usual choice.
  • Pressure duty: use performance data at the same discharge pressure the plant actually needs. Remember that each extra bar typically costs about 7% more power.
  • Power boundary: use total package electrical input (main motor, fan motor, drive losses and controls) for every machine, not shaft power for one and input power for another.
  • Operating range: respect each machine’s verified minimum and maximum stable flow. A VSD machine below its minimum speed will start load/unload cycling.
  • Part-load curve: interpolate only between verified points. Never extrapolate a curve beyond its data without flagging it.
  • Availability: exclude machines that are under maintenance, held for repair or deliberately locked out.

Inputs the calculator needs

InputTypical sourceWhy it matters
Machine list and control typeNameplates, controller menusFixed-speed load/unload, modulation and VSD machines behave very differently at part load
Full-load FAD at duty pressureData sheet or acceptance testSets each machine’s contribution
Loaded and unloaded package kWPower loggingUnloaded power is often a large hidden loss
Part-load power curveVSD data sheet points or logged dataDefines the cost of trimming
Minimum stable flowController settings, data sheetPrevents infeasible trim states
Required pressure at the plantPressure profiling at critical usersSets the duty pressure for all data
Demand profileFlow logging or a demand duration curveWeights each state by hours
Reserve ruleSite criticality policyRules out states that leave the plant exposed

If the demand profile is not yet known, build it first with the air demand duration curve tool or from a logging exercise.

Method: how the calculation works

  1. List every combination. For a fleet of n machines there are up to 2n − 1 on/off combinations. Unavailable machines are removed first.
  2. Check feasibility. A combination is feasible at a demand Q only if the sum of the maximum flows of the online machines is at least Q, and the trim machine can deliver the remainder within its stable range.
  3. Assign base and trim. Base machines run fully loaded. One machine, normally the VSD unit or the machine with the flattest part-load curve, takes the balance.
  4. Calculate power. Total kW = sum of loaded kW of base machines + trim machine kW at its part-load flow. For a fixed-speed trim machine on load/unload control, a simple model is kW ≈ (load fraction × loaded kW) + ((1 − load fraction) × unloaded kW), adjusted upward where receiver storage is small and blow-down cycles are frequent.
  5. Check reserve. Apply the reserve rule. For N+1, the online machines plus any standby that can start in time must still cover the demand with the largest running unit lost.
  6. Rank. Sort feasible states by total kW and show the specific power, kW ÷ m³/min delivered, for each.
  7. Weight across the profile. Annual kWh = Σ (kW of the chosen state in each band × hours in that band).

Worked example: three machines, one demand point

The figures below are illustrative assumptions, chosen to show the method. Use your own logged data for a real decision.

  • Machine A: fixed-speed, 6.0 m³/min, 40 kW loaded, about 12 kW unloaded.
  • Machine B: identical to A.
  • Machine C: VSD, stable range 2.0–7.5 m³/min; at 4.0 m³/min it draws about 27 kW.
  • Plant demand: 10.0 m³/min at 7 bar (101.5 psig).
StateBaseTrimTotal kWSpecific power, kW per m³/minN+1 check
A + BA at 6.0B at 4.0 (67% loaded)26.7 + 4.0 + 40 = 70.77.07Passes if C starts in time: 6.0 + 7.5 = 13.5
A + CA at 6.0C at 4.040 + 27 = 67.06.70Passes if B starts in time: 12.0 left if C trips, 13.5 left if A trips
B + CB at 6.0C at 4.067.06.70Passes if A starts in time
C alone––Infeasible–C maximum 7.5 is below demand

The A + C (or B + C) state saves about 3.7 kW against A + B at the same delivered flow. Over 6,000 running hours that is about 22,000 kWh a year from a settings change alone. Alternating A and B as the base machine also evens out running hours between them.

How to read the results

The ranking is a guide, not an instruction to change settings blindly. Look at these points before acting:

  • Margin between states: if the best and second-best states differ by less than the uncertainty in your power data, choose the one that is simpler to control or better for maintenance.
  • Switching points in a sweep: a recommended change at, say, 8 m³/min needs a pressure band or sequencer logic that actually switches there without hunting.
  • Trim range: if the VSD machine sits near its minimum speed for long hours, a smaller trim machine or more storage may beat any dispatch rule.
  • VSD gap: when the VSD’s range cannot fill the gap between fixed-speed steps, the fleet will cycle. The sweep will show these bands clearly.
  • Unloaded hours: a state with many unloaded hours on a large machine usually points to oversizing or a control problem, covered on our unload and idle loss reduction page.

Limits of the calculation

The calculator assumes steady demand within each band. Real plants see transient peaks, and those are handled by receiver storage and pressure band design rather than by dispatch alone; the receiver transient storage calculator covers that side. It also assumes the controls can actually hold the chosen state. Many older rooms rely on cascaded pressure switches, which drift and widen the pressure band. A proper sequencer or master controller is often needed to put the best dispatch into practice reliably.

Data quality is the biggest limit. Unloaded power, VSD part-load curves and real FAD at the site’s inlet temperature are frequently different from catalogue values, especially in Hyderabad’s summer when compressor rooms run hot. Logged package kW and flow over at least a representative week give far more trustworthy results than data sheets.

How Reddy Compressors helps

Reddy Compressors has worked with compressed-air users since 2002 as an independent multi-brand specialist. We are not an authorised distributor of any brand, which lets us look at mixed fleets of ELGi, Atlas Copco, Ingersoll Rand, KAESER, Chicago Pneumatic, Sullair, Doosan, Kirloskar and other machines on the same neutral basis. We have tie-ups with all major and reputed brands.

  • Power and flow logging to build a real demand profile and real part-load curves for each machine.
  • Air audits by the ISO 11011 method, including dispatch analysis and pressure profiling.
  • Recommendations on base, trim and VSD roles, pressure bands and sequencer settings, linked to our compressor sequencers guidance.
  • Supply of new or used/refurbished compressors where the fleet lacks a suitable trim machine, and rental cover while changes are made.
  • Service, AMC and spare parts for the whole fleet, so that machines perform close to their data.

Our office is at Tarnaka, Secunderabad. Our team of more than 20 service engineers and technicians covers the whole of Telangana and Andhra Pradesh, and we supply equipment, rentals and spares across India.

What to send us

  • Make, model and nameplate photo of each compressor, with its control type.
  • Running and loaded hours from each controller.
  • Required pressure at the critical point of use.
  • Any logged kW, flow or pressure data, or the shift pattern if none exists.
  • Your reserve requirement, such as N+1 for critical production.
  • Details of receivers, dryers and the current sequencing method.

Frequently asked questions

Which compressor should be the base load machine?

The base machine should be the one with the best specific power when fully loaded, because it will spend most hours at that point. Fixed-speed screw compressors are usually most efficient fully loaded, so they suit base duty. The trim role should go to the machine with the flattest part-load curve, normally a VSD unit. Rotate base duty between identical machines to even out wear and service intervals.

Is it better to run two compressors at part load or one fully loaded?

In most cases one machine fully loaded plus one trim machine uses less power than two machines both partly unloaded. Fixed-speed machines on load/unload control still draw a substantial share of loaded power while unloaded, so two partly loaded units pay that penalty twice. The calculator shows the exact difference for your machines once real loaded and unloaded power figures are entered.

What is a good specific power for a compressor room?

Specific power is total electrical input divided by delivered flow, in kW per m³/min, and it depends heavily on pressure, machine size and control type. Rather than chasing a single target figure, compare your room against the data sheets of your own machines at your duty pressure. A room that runs well above the machines’ rated values usually has a dispatch, unloading or pressure problem to fix.

Can a VSD compressor solve all part-load losses?

No. A VSD machine is efficient only within its stable speed range. If demand drops below that range, it starts load/unload cycling, and if the gap between fixed-speed machines is larger than the VSD range, the fleet hunts between states. Correct sizing of the trim machine, enough receiver storage and coordinated control are needed alongside the VSD itself.

How much data do I need for a reliable dispatch calculation?

At minimum you need loaded and unloaded package power, FAD at duty pressure and the stable range of each machine, plus a demand profile. Logging power and flow for at least one representative week, covering production days, weekends and shift changes, gives a much more trustworthy result than catalogue data. Seasonal effects such as hot summer inlet air should be checked separately.

Do I need a master controller to use the results?

Not always. A small room with two or three machines can sometimes implement a good dispatch with carefully staggered pressure bands. Larger or mixed-brand rooms usually benefit from a sequencer or master controller, because cascaded pressure settings widen the band, raise average pressure and make it hard to hold the chosen base and trim roles consistently.

Calculators and worked examples

These tools give indicative figures for screening, comparison and for preparing an enquiry. They run in your browser and send nothing. No prices or tariffs are assumed: enter your own to see costs. Efficiencies and other figures shown are example values: replace them with your own. Results are not a performance guarantee or a design certificate; final selection is confirmed by a service engineer against the machine data sheet and the site.

Part-load fleet dispatch (single demand point)

The worked example below shows the method with fixed numbers. Turn on JavaScript to change the inputs.

Worked example

Inputs
  • Plant demand to be met (m³/min free air): 10
  • Machine A: type: Fixed speed, load/unload
  • Machine A: full-load flow, FAD at duty pressure (m³/min): 6
  • Machine A: package power at full flow (kW): 40
  • Machine A, fixed speed only: unloaded power (kW): 12
  • Machine A, VSD only: minimum stable flow (m³/min): 0
  • Machine A, VSD only: power at minimum flow (kW): 0
  • Machine B: type: Fixed speed, load/unload
  • Machine B: full-load flow, FAD at duty pressure (m³/min): 6
  • Machine B: package power at full flow (kW): 40
  • Machine B, fixed speed only: unloaded power (kW): 12
  • Machine B, VSD only: minimum stable flow (m³/min): 0
  • Machine B, VSD only: power at minimum flow (kW): 0
  • Machine C: type: Variable speed (VSD)
  • Machine C: full-load flow, FAD at duty pressure (m³/min): 7.5
  • Machine C: package power at full flow (kW): 48
  • Machine C, fixed speed only: unloaded power (kW): 0
  • Machine C, VSD only: minimum stable flow (m³/min): 2
  • Machine C, VSD only: power at minimum flow (kW): 15
  • Running hours per year at this demand: 6,000
Result
  • 1. A + C: 67 kW, 6.7 kW per m³/min; trim C at 4 m³/min (VSD), others fully loaded
  • 2. B + C: 67 kW, 6.7 kW per m³/min; trim C at 4 m³/min (VSD), others fully loaded
  • 3. A + B: 70.7 kW, 7.07 kW per m³/min; trim A at 4 m³/min (67% loaded), others fully loaded
  • Lowest-power state: A + C trim C at 4 m³/min (VSD), others fully loaded
  • Specific power of that state: 6.7 kW per m³/min
  • Annual energy in that state: 4,02,000 kWh per year
  • N+1 check (lose machine C): Passes other available machines can give 12 m³/min against 10 m³/min demand
  • Lowest-power state that also passes N+1: Same as above
  • Saving against the next higher-power state (A + B): 3.67 kW = 22,000 kWh per year

Method. Single-demand-point mode. Every on/off combination of the available machines is tried, with each online machine in turn as the trim machine. Base machines run fully loaded at their FAD and full-flow kW; the trim machine takes the remainder. A state is feasible only if the remainder is above 0, no more than the trim machine’s full flow, and (for a VSD trim) not below its minimum stable flow. Fixed-speed trim on load/unload: kW = x × loaded kW + (1 − x) × unloaded kW, with x = trim flow ÷ full flow (ignores extra blowdown losses with small storage). VSD trim: kW interpolated linearly between the minimum-flow and full-flow points. Specific power = total kW ÷ demand. N+1 check: with the largest online machine lost, all other available machines together must still cover the demand (assumes standby machines can start in time). Annual kWh = kW × hours at this demand. The lowest-power state that also passes N+1 is shown when the cheapest state does not. Use package kW and FAD at the same duty pressure for every machine. Not included: the demand sweep, annual load profile and scenario modes described on the page; run the tool once per demand band and weight each result by the hours in that band (annual kWh = Σ kW × hours).

What to take from it. Run the base machines fully loaded and give the trim role to the machine with the flattest part-load curve; two fixed-speed machines both partly unloaded is usually the most expensive way to meet the same flow.

Technical content reviewed by D. Srinivas Reddy, Managing Partner and service engineer, Reddy Compressors. Last updated 17 October 2026. How our engineering content is reviewed.